Share Aug. 28 project update on Facebook
Share Aug. 28 project update on Linkedin
Email Aug. 28 project update link
Work on Archwood Road has been temporarily halted due to an equipment failure experienced by the City’s contractor. The contractor anticipates having the equipment repaired and back on site the week of Sept. 1, allowing work to resume that same week.
The project remains on schedule to be completed within the original 8 to 10-week timeframe.
Thank you for your continued patience and understanding.
Share Aug. 8 project update on Facebook
Share Aug. 8 project update on Linkedin
Email Aug. 8 project update link
This week's progress:
- Completed install of sanitary pipe under Interstate 394
- Began installation of sanitary pipe on Archwood Road
Next week's schedule
- Complete installation of sanitary pipe on Archwood Road
- Begin making connections to existing infrastructure
Share July 25 project update on Facebook
Share July 25 project update on Linkedin
Email July 25 project update link
This week's progress:
- Pipe fusing complete
- Sanitary sewer pipe install continues
Next week's activity:
- Continue installing sanitary pipe
Share July 18, project update on Facebook
Share July 18, project update on Linkedin
Email July 18, project update link
This week's progress
- Sanitary sewer pipe installation continues
- Pipe fusing continues
Next weeks' activities
- Continue installing sanitary sewer pipe
- Complete pipe fusing
Share July 11, project update on Facebook
Share July 11, project update on Linkedin
Email July 11, project update link
This week's progress:
- Traffic control installed
- Materials arrived on site
- Fusing of sanitary sewer pipe began
- Tree and pavement removal began
Next week's activities include:
- Beginning installation sanitary sewer pipe
- Removals continue
Share July 3, project update on Facebook
Share July 3, project update on Linkedin
Email July 3, project update link
On Monday, July 7, the city's contractor will begin work on the project.
Archwood Road Closure
Archwood Road will be closed from Wayzata Boulevard South to approximately 200 feet south of the intersection beginning July 7. The closure is expected to last 8 to 10 weeks. This will allow crews to install new sanitary sewer pipe. Traffic will be detoured south on Ford Road, and west along Crestridge Drive.