July 1, project update

Area 1 is complete

All phases in Area 2 have been delayed due to weather conditions.

  • Maywood Lane, Jane Lane- Phase three delayed due to weather
  • Carleton Road, Birchwood Lane, Arlington Drive, Royal Oaks Drive, Merillee Drive, Valley Road and Pioneer Drive- Phase one and two in progress
  • Winterset Drive, Diane Drive, Barbara Drive, Joanne Lane and Church Lane- Parking restrictions lifted until further notice.