2026 Mill and Pave project

Share 2026 Mill and Pave project on Facebook Share 2026 Mill and Pave project on X (formerly Twitter) Share 2026 Mill and Pave project on Linkedin Email 2026 Mill and Pave project link

The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.

Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase 1

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase 2

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase 3

  • A new layer of asphalt is applied to the roadway.

The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.

Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase 1

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase 2

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase 3

  • A new layer of asphalt is applied to the roadway.
  • Project begins in Area 1 June 2

    Share Project begins in Area 1 June 2 on Facebook Share Project begins in Area 1 June 2 on X (formerly Twitter) Share Project begins in Area 1 June 2 on Linkedin Email Project begins in Area 1 June 2 link

    Progress on the 2026 Mill and Pave project is set to begin on June 2 in Area 1. This area includes (from east to west):

    • Gizmo Lane
    • F Street
    • E Street
    • Delta Avenue
    • Chippewa Road
    • Birch Place
    • W 34th Circle
    • 34th St West.

    Progress on the 2026 Mill and Pave project is set to begin on June 2 in Area 1. This area includes (from east to west):

    • Gizmo Lane
    • F Street
    • E Street
    • Delta Avenue
    • Chippewa Road
    • Birch Place
    • W 34th Circle
    • 34th St West.
  • 2026 Mill and Pave map posted

    Share 2026 Mill and Pave map posted on Facebook Share 2026 Mill and Pave map posted on X (formerly Twitter) Share 2026 Mill and Pave map posted on Linkedin Email 2026 Mill and Pave map posted link

    The 2026 Mill and Pave map has been posted. The map indicates areas that will be constructed during the summer of 2026.

    The 2026 Mill and Pave map has been posted. The map indicates areas that will be constructed during the summer of 2026.

  • 2025 Mill and Overlay project complete

    Share 2025 Mill and Overlay project complete on Facebook Share 2025 Mill and Overlay project complete on X (formerly Twitter) Share 2025 Mill and Overlay project complete on Linkedin Email 2025 Mill and Overlay project complete link

    With cooler temperatures moving in, the 2025 Mill and Overlay project is now complete. Several streets were not completed this summer due to continued wet conditions. Those streets include:

    • Gizmo Lane
    • F Street
    • E Street
    • Chippewa Road
    • Birch Place
    • Atwater Street
    • W 34th Circle
    • W 34th Street
    • Delta Ave

    Those streets will be completed in 2026.

    With cooler temperatures moving in, the 2025 Mill and Overlay project is now complete. Several streets were not completed this summer due to continued wet conditions. Those streets include:

    • Gizmo Lane
    • F Street
    • E Street
    • Chippewa Road
    • Birch Place
    • Atwater Street
    • W 34th Circle
    • W 34th Street
    • Delta Ave

    Those streets will be completed in 2026.

  • Oct. 20 project update

    Share Oct. 20 project update on Facebook Share Oct. 20 project update on X (formerly Twitter) Share Oct. 20 project update on Linkedin Email Oct. 20 project update link

    Due to weather conditions, phase 3 will begin on Ann Lane and Sandra Lane on Oct. 22.

    Please have all vehicles moved off the street for these operations.

    Due to weather conditions, phase 3 will begin on Ann Lane and Sandra Lane on Oct. 22.

    Please have all vehicles moved off the street for these operations.

  • Oct. 15 project update

    Share Oct. 15 project update on Facebook Share Oct. 15 project update on X (formerly Twitter) Share Oct. 15 project update on Linkedin Email Oct. 15 project update link

    Ann Lane and Sandra Lane will begin Phase 3 on Monday, Oct. 20, pending favorable weather. Please have all vehicles moved off the street.

    Ann Lane and Sandra Lane will begin Phase 3 on Monday, Oct. 20, pending favorable weather. Please have all vehicles moved off the street.

  • Oct. 8 project update

    Share Oct. 8 project update on Facebook Share Oct. 8 project update on X (formerly Twitter) Share Oct. 8 project update on Linkedin Email Oct. 8 project update link

    Phase 1 will start the week of Oct. 13 for Ann Lane and Sandra Lane.

    Phase 1 will start the week of Oct. 13 for Ann Lane and Sandra Lane.

  • Oct. 2 project update

    Share Oct. 2 project update on Facebook Share Oct. 2 project update on X (formerly Twitter) Share Oct. 2 project update on Linkedin Email Oct. 2 project update link

    Area 3 complete. Parking restrictions are lifted.

    Area 4, phase 1 to begin the week of Oct. 6.

    Area 3 complete. Parking restrictions are lifted.

    Area 4, phase 1 to begin the week of Oct. 6.

  • Sept. 24 project update

    Share Sept. 24 project update on Facebook Share Sept. 24 project update on X (formerly Twitter) Share Sept. 24 project update on Linkedin Email Sept. 24 project update link

    Phase 1 and 2 in progress for McKenzie Blvd

    Phase 3 week of Sept 22nd : Skyview Dr, Highland Road, Belvior Dr, and Thomas Ave.

    Phase 3 week of Sept 29th: Redding Ridge Dr, Red Oak Rdg, and McKenzie Blvd.

    Phase 1 and 2 in progress for McKenzie Blvd

    Phase 3 week of Sept 22nd : Skyview Dr, Highland Road, Belvior Dr, and Thomas Ave.

    Phase 3 week of Sept 29th: Redding Ridge Dr, Red Oak Rdg, and McKenzie Blvd.

  • Sept. 15 project update

    Share Sept. 15 project update on Facebook Share Sept. 15 project update on X (formerly Twitter) Share Sept. 15 project update on Linkedin Email Sept. 15 project update link

    Updates listed for area 3.

    Phase 1

    Main milling is completed. Detail milling in progress.


    Phase 2

    In progress.


    Phase 3

    Paving Day Place and Victoria Drive on Sept. 16.

    Wendover Court Ct and Skyview Road (North) Sept. 17 pending weather.

    Updates listed for area 3.

    Phase 1

    Main milling is completed. Detail milling in progress.


    Phase 2

    In progress.


    Phase 3

    Paving Day Place and Victoria Drive on Sept. 16.

    Wendover Court Ct and Skyview Road (North) Sept. 17 pending weather.

  • Sept. 1 project update

    Share Sept. 1 project update on Facebook Share Sept. 1 project update on X (formerly Twitter) Share Sept. 1 project update on Linkedin Email Sept. 1 project update link

    Area 2 is complete.

    Area 3 begins this week.

    Area 2 is complete.

    Area 3 begins this week.