2026 Mill and Pave project
The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.
Work on this project has been completed for the year.
Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.
Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.
Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.
Street overlay projects proceed as follows:
Pre-phase
- Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion
Phase I
- The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase
Phase II
- Manholes and gate valves are raised to accommodate new the new layers of asphalt.
Phase III
- A new layer of asphalt is applied to the roadway.
The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.
Work on this project has been completed for the year.
Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.
Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.
Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.
Street overlay projects proceed as follows:
Pre-phase
- Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion
Phase I
- The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase
Phase II
- Manholes and gate valves are raised to accommodate new the new layers of asphalt.
Phase III
- A new layer of asphalt is applied to the roadway.
-
Paving next week on Woodland Circle, Stoneybrook Court, Maplewood Lane and more
Share Paving next week on Woodland Circle, Stoneybrook Court, Maplewood Lane and more on Facebook Share Paving next week on Woodland Circle, Stoneybrook Court, Maplewood Lane and more on X (formerly Twitter) Share Paving next week on Woodland Circle, Stoneybrook Court, Maplewood Lane and more on Linkedin Email Paving next week on Woodland Circle, Stoneybrook Court, Maplewood Lane and more linkMain milling has been completed for half of Area 5. Due to Centerpoint Energy's work, the second half of Area 5 will be milled at a later date.
Phase II has been initiated.
Phase III (paving) will begin Monday on Woodland Circle and Stoneybrook Court. Maplewood Lane and Scenic Drive will begin Tuesday. Ivy Lane and Picha Lane begin Wednesday. Stoneybrook Drive will begin Thursday. These dates are subject to change, depending on weather.
Please do not park on the street. Stay off fresh tack oil.
Main milling has been completed for half of Area 5. Due to Centerpoint Energy's work, the second half of Area 5 will be milled at a later date.
Phase II has been initiated.
Phase III (paving) will begin Monday on Woodland Circle and Stoneybrook Court. Maplewood Lane and Scenic Drive will begin Tuesday. Ivy Lane and Picha Lane begin Wednesday. Stoneybrook Drive will begin Thursday. These dates are subject to change, depending on weather.
Please do not park on the street. Stay off fresh tack oil.
-
Area 6 complete
Share Area 6 complete on Facebook Share Area 6 complete on X (formerly Twitter) Share Area 6 complete on Linkedin Email Area 6 complete linkPaving operations in area 6 are complete. Whitegate Lane will be milled and paved at a later date due to a utility project.
Area 5 will begin Phase I beginning the week of Aug. 24. Area 5 will be milled in segments due to Centerpoint Energy's work.
The first segment to be milled includes the following
- Creekside Lane
- Scenic Road
- Creekside Circle
- Boulder Creek Drive
- Stoneybrook Drive
- Woodland Circle
- Maplewood Lane
- Holiday Way
- Scenic Place
- Ivy Lane
- Picha Lane
- Stodola Road
- High Park Drive
- Creek Park Drive
Paving operations in area 6 are complete. Whitegate Lane will be milled and paved at a later date due to a utility project.
Area 5 will begin Phase I beginning the week of Aug. 24. Area 5 will be milled in segments due to Centerpoint Energy's work.
The first segment to be milled includes the following
- Creekside Lane
- Scenic Road
- Creekside Circle
- Boulder Creek Drive
- Stoneybrook Drive
- Woodland Circle
- Maplewood Lane
- Holiday Way
- Scenic Place
- Ivy Lane
- Picha Lane
- Stodola Road
- High Park Drive
- Creek Park Drive
-
Area 6 work continues
Share Area 6 work continues on Facebook Share Area 6 work continues on X (formerly Twitter) Share Area 6 work continues on Linkedin Email Area 6 work continues linkPhase II is complete in area 6. Phase III will start this week. Drive with caution.
Be aware: wet tack oil is present on the roadway.
Phase II is complete in area 6. Phase III will start this week. Drive with caution.
Be aware: wet tack oil is present on the roadway.
-
No on-street parking in Area 6 tomorrow
Share No on-street parking in Area 6 tomorrow on Facebook Share No on-street parking in Area 6 tomorrow on X (formerly Twitter) Share No on-street parking in Area 6 tomorrow on Linkedin Email No on-street parking in Area 6 tomorrow linkArea 3 is complete.
Work will begin in Area 6 beginning tomorrow, July 30. The area includes sections of:
- Black Oaks Lane
- Legacy Oaks Trail
- Ranchview Lane S
- Townes Lane
- Townes Road
- Whitegate Lane
- Gleason Acres Drive
See the project map for further details. Please, no on street parking from 6 a.m. - 6 p.m. during the project.
Area 3 is complete.
Work will begin in Area 6 beginning tomorrow, July 30. The area includes sections of:
- Black Oaks Lane
- Legacy Oaks Trail
- Ranchview Lane S
- Townes Lane
- Townes Road
- Whitegate Lane
- Gleason Acres Drive
See the project map for further details. Please, no on street parking from 6 a.m. - 6 p.m. during the project.
-
Work on Amy Lane and Emerald Trail continues
Share Work on Amy Lane and Emerald Trail continues on Facebook Share Work on Amy Lane and Emerald Trail continues on X (formerly Twitter) Share Work on Amy Lane and Emerald Trail continues on Linkedin Email Work on Amy Lane and Emerald Trail continues linkCORRECTION: A previous version of this story had the date listed as June 29. It has been changed to reflect the correct date, July 29.
Phase I and II will be complete tomorrow on Amy Lane and Emerald Trail tomorrow.
Phase III will begin on Wednesday, July 29. Stay off the street and watch for tack oil on the street.
CORRECTION: A previous version of this story had the date listed as June 29. It has been changed to reflect the correct date, July 29.
Phase I and II will be complete tomorrow on Amy Lane and Emerald Trail tomorrow.
Phase III will begin on Wednesday, July 29. Stay off the street and watch for tack oil on the street.
-
Phase I begins in area 3 tomorrow; Bantas Point complete
Share Phase I begins in area 3 tomorrow; Bantas Point complete on Facebook Share Phase I begins in area 3 tomorrow; Bantas Point complete on X (formerly Twitter) Share Phase I begins in area 3 tomorrow; Bantas Point complete on Linkedin Email Phase I begins in area 3 tomorrow; Bantas Point complete linkPhase III has been completed in the Bantas Point area.
Phase I is set to begin in area 3 on Thursday, July 31. That area includes sections of:
- Amy Lane
- Emerald Trail
Phase III has been completed in the Bantas Point area.
Phase I is set to begin in area 3 on Thursday, July 31. That area includes sections of:
- Amy Lane
- Emerald Trail
-
Paving on Bantas Point Road tomorrow, July 21
Share Paving on Bantas Point Road tomorrow, July 21 on Facebook Share Paving on Bantas Point Road tomorrow, July 21 on X (formerly Twitter) Share Paving on Bantas Point Road tomorrow, July 21 on Linkedin Email Paving on Bantas Point Road tomorrow, July 21 linkTeams will begin paving Bantas Point Road tomorrow, July 21. Please have all vehicles off the road. Parking is available on the north side of the bridge for residents that need to park on the street.
Avoid driving on the tack oil, which will spread to driveways.
Teams will begin paving Bantas Point Road tomorrow, July 21. Please have all vehicles off the road. Parking is available on the north side of the bridge for residents that need to park on the street.
Avoid driving on the tack oil, which will spread to driveways.
-
Bantas Point Lane Paving today
Share Bantas Point Lane Paving today on Facebook Share Bantas Point Lane Paving today on X (formerly Twitter) Share Bantas Point Lane Paving today on Linkedin Email Bantas Point Lane Paving today linkPhase III is complete for Crosby Bove and Crosby Road
Paving (phase III) begins today for Bantas Point Lane and Pine Street. Please keep all vehicles off the street. Park on Bantas Point Road if needed.
Teams will return on Tuesday, July 21 to complete Bantas Point Road.
There will be a tack oil sprayed on the road surface before asphalt is applied. Drive with caution. Wet tack oil will transfer to driveways. When the road is paved, it is okay to drive on. Please allow 3 - 7 days for the asphalt to start the curing process.
Thank you for your cooperation and patience as this project progresses.
Phase III is complete for Crosby Bove and Crosby Road
Paving (phase III) begins today for Bantas Point Lane and Pine Street. Please keep all vehicles off the street. Park on Bantas Point Road if needed.
Teams will return on Tuesday, July 21 to complete Bantas Point Road.
There will be a tack oil sprayed on the road surface before asphalt is applied. Drive with caution. Wet tack oil will transfer to driveways. When the road is paved, it is okay to drive on. Please allow 3 - 7 days for the asphalt to start the curing process.
Thank you for your cooperation and patience as this project progresses.
-
Phase III begins on Bantas Point Lane Thursday
Share Phase III begins on Bantas Point Lane Thursday on Facebook Share Phase III begins on Bantas Point Lane Thursday on X (formerly Twitter) Share Phase III begins on Bantas Point Lane Thursday on Linkedin Email Phase III begins on Bantas Point Lane Thursday linkPhase III is complete for Crosby Cove, but will continue tomorrow on Crosby Road. Paving operations will begin Thursday, July 16 on Bantas Point Lane Thursday.
Please have all vehicles off the road.Phase III is complete for Crosby Cove, but will continue tomorrow on Crosby Road. Paving operations will begin Thursday, July 16 on Bantas Point Lane Thursday.
Please have all vehicles off the road. -
Area 2 Phase II completed; paving tomorrow
Share Area 2 Phase II completed; paving tomorrow on Facebook Share Area 2 Phase II completed; paving tomorrow on X (formerly Twitter) Share Area 2 Phase II completed; paving tomorrow on Linkedin Email Area 2 Phase II completed; paving tomorrow linkPhase II is complete in Area 2. Phase III will begin for Crosby Road and Crosby Cove tomorrow.
No parking on the street tomorrow.
Phase II is complete in Area 2. Phase III will begin for Crosby Road and Crosby Cove tomorrow.
No parking on the street tomorrow.
-
-