Pipe installation through this week
Last week's progress
- The city's contractor removed accumulated sediment from the drainage ditch and started removing and replacing storm sewer pipe in the back yards on Saddlewood Drive
This week's activities include:
- Contractor will continue to remove and replace storm sewer pipe
- Xcel Energy and Comcast will finish utility work
Substantial completion of the project is expected by Nov. 6, with vegetation establishment in the spring of 2027