Pipe installation through this week

Last week's progress

  • The city's contractor removed accumulated sediment from the drainage ditch and started removing and replacing storm sewer pipe in the back yards on Saddlewood Drive

This week's activities include:

  • Contractor will continue to remove and replace storm sewer pipe
  • Xcel Energy and Comcast will finish utility work

Substantial completion of the project is expected by Nov. 6, with vegetation establishment in the spring of 2027