Eastbound Gleason Lake Road to open Saturday

Eastbound Gleason Lake Road (CR 15) will reopen Saturday, Sept. 12.

This week's progress included:

  • Drilling completed
  • Curb completed
  • Paving completed

Next week's activities include

  • Continued restoration
  • Remaining punch list and clean-up items