Lane closure continues for manhole work

The Gleason Lake Road (CR 15) eastbound lane will remain closed through Sept. 14 to install sanitary force main along Gleason Lake Road and make connection to a manhole.

This week’s progress included:

  • Drilling continued
  • Manhole installed

Next week’s activities include:

  • Drilling will be completed
  • Curb pouring
  • Restoration will begin

Please be aware of traffic control changes and watch for changing traffic patterns.