Project underway, Lane closure begins Aug. 31

Project began Aug. 24, 2026

The Gleason Lake Road (CR 15) eastbound lane will be closed beginning Monday, Aug. 31 for two weeks to install sanitary force main along Gleason Lake Road and make connection to a manhole. Please see detour map here.

This week’s progress included:

  • Locating existing utilities
  • Drilling began

Next week’s activities include:

  • Drilling will continue
  • Pipe fusing

Please be aware of traffic control changes and watch for changing traffic patterns.