May 16, project update
This week’s progress:
- Traffic control and detour in place
- Pavement removals began
- Construction materials arrived on site
- Sanitary pipe fused
- Sanitary sewer pipe installation began
Next week’s activities include:
- Installing sanitary sewer pipe
- Installing manholes