Project update June 12, construction underway

On June 11, the project began with work primarily confined to the south side of Cedar Lake Road.

This week's progress:

  • Traffic control was installed and traffic was shifted north on Cedar Lake Road
  • Curb and sidewalk removals began
  • Tree removals were completed on the south side of Cedar Lake Road

Next weeks activities:

  • Removal of curb and sidewalk will continue
  • Storm sewer rehabilitation will begin

Please be aware of traffic control changes and watch for shifting traffic patterns.