Cedar Lake Road Improvement Project

Share Cedar Lake Road Improvement Project on Facebook Share Cedar Lake Road Improvement Project on X (formerly Twitter) Share Cedar Lake Road Improvement Project on Linkedin Email Cedar Lake Road Improvement Project link
Intersection of Cedar Hills Drive and Cedar Lake Road with vehicles

The city is proposing street improvements along Cedar Lake Road from Hopkins Crossroad to Hwy 169. The project proposes improvements to pavement, damaged curb and sidewalks, pedestrian ramps, utility castings, traffic signals and pavement markings.

MnDOT will also begin improvements on the intersection of Cedar Lake Road and Jordan Avenue near the Hwy 169 interchange. This work is scheduled to begin in June of 2026.

The city is proposing street improvements along Cedar Lake Road from Hopkins Crossroad to Hwy 169. The project proposes improvements to pavement, damaged curb and sidewalks, pedestrian ramps, utility castings, traffic signals and pavement markings.

MnDOT will also begin improvements on the intersection of Cedar Lake Road and Jordan Avenue near the Hwy 169 interchange. This work is scheduled to begin in June of 2026.

  • Closure to end Aug. 16

    Share Closure to end Aug. 16 on Facebook Share Closure to end Aug. 16 on X (formerly Twitter) Share Closure to end Aug. 16 on Linkedin Email Closure to end Aug. 16 link

    Road Closure

    Cedar Lake Road is closed at the following locations:

    1. Between Hedberg Drive and Cedar Hills Boulevard
    2. Between Royals Drive and Marcy Lane
    3. Between Ford Road and Cedar Crest Road West

    Access to homes, businesses and side streets will remain accessible during the closure. Please see map for detour routes. This closure will end the evening of Aug. 26.

    This week’s progress:

    • Concrete work was completed
    • Median construction was completed
    • Roadway milling was completed

    Next week’s activities:

    • Roadway paving
    • Roadway striping
    • Sign installation
    • Signal systems will be completed
    • Miscellaneous restoration and punch list items

    Road Closure

    Cedar Lake Road is closed at the following locations:

    1. Between Hedberg Drive and Cedar Hills Boulevard
    2. Between Royals Drive and Marcy Lane
    3. Between Ford Road and Cedar Crest Road West

    Access to homes, businesses and side streets will remain accessible during the closure. Please see map for detour routes. This closure will end the evening of Aug. 26.

    This week’s progress:

    • Concrete work was completed
    • Median construction was completed
    • Roadway milling was completed

    Next week’s activities:

    • Roadway paving
    • Roadway striping
    • Sign installation
    • Signal systems will be completed
    • Miscellaneous restoration and punch list items
  • Road closures continue; concrete and median work this week

    Share Road closures continue; concrete and median work this week on Facebook Share Road closures continue; concrete and median work this week on X (formerly Twitter) Share Road closures continue; concrete and median work this week on Linkedin Email Road closures continue; concrete and median work this week link

    Road Closure

    Cedar Lake Road is closed at the following locations:

    1. Between Hedberg Drive and Cedar Hills Boulevard
    2. Between Royals Drive and Marcy Lane
    3. Between Ford Road and Cedar Crest Road West

    Access to homes, businesses and side streets will remain accessible during the closure. Please see map for detour routes.

    Last week’s progress:

    • Concrete pouring continued
    • Wall construction completed
    • Median construction began

    This week’s activities:

    • Concrete work will continue
    • Median construction will be completed
    • Roadway milling will begin

    Road Closure

    Cedar Lake Road is closed at the following locations:

    1. Between Hedberg Drive and Cedar Hills Boulevard
    2. Between Royals Drive and Marcy Lane
    3. Between Ford Road and Cedar Crest Road West

    Access to homes, businesses and side streets will remain accessible during the closure. Please see map for detour routes.

    Last week’s progress:

    • Concrete pouring continued
    • Wall construction completed
    • Median construction began

    This week’s activities:

    • Concrete work will continue
    • Median construction will be completed
    • Roadway milling will begin
  • Road closures coming Aug. 12

    Share Road closures coming Aug. 12 on Facebook Share Road closures coming Aug. 12 on X (formerly Twitter) Share Road closures coming Aug. 12 on Linkedin Email Road closures coming Aug. 12 link

    Road Closure

    Cedar Lake Road will be closed in the following locations beginning August 12:

    1. Between Hedberg Drive and Cedar Hills Boulevard
    2. Between Royals Drive and Marcy Lane
    3. Between Ford Road and Cedar Crest Road West

    Access to homes, businesses and side streets will remain accessible during the closure. The north detour route will send motorists north on Hwy 169 to west 394, then south on Hopkins Crossroad. The south detour will send motorists south on Hopkins Crossroad, east on Minnetonka Boulevard then north on Hwy 169.

    During this closure, raised center medians will be installed to enhance pedestrian safety. This closure is expected to last two weeks.

    Project progress

    This week’s progress:

    1. Concrete pouring continued
    2. Wall construction continued
    3. Asphalt patching continued

    Next week’s activities:

    1. Concrete pouring will continue
    2. Wall construction will continue
    3. Asphalt patching will continue
    4. Center median construction will begin

    Please be aware of traffic control changes and watch for shifting traffic patterns.

    Road Closure

    Cedar Lake Road will be closed in the following locations beginning August 12:

    1. Between Hedberg Drive and Cedar Hills Boulevard
    2. Between Royals Drive and Marcy Lane
    3. Between Ford Road and Cedar Crest Road West

    Access to homes, businesses and side streets will remain accessible during the closure. The north detour route will send motorists north on Hwy 169 to west 394, then south on Hopkins Crossroad. The south detour will send motorists south on Hopkins Crossroad, east on Minnetonka Boulevard then north on Hwy 169.

    During this closure, raised center medians will be installed to enhance pedestrian safety. This closure is expected to last two weeks.

    Project progress

    This week’s progress:

    1. Concrete pouring continued
    2. Wall construction continued
    3. Asphalt patching continued

    Next week’s activities:

    1. Concrete pouring will continue
    2. Wall construction will continue
    3. Asphalt patching will continue
    4. Center median construction will begin

    Please be aware of traffic control changes and watch for shifting traffic patterns.

  • Wall construction and concrete pouring to continue

    Share Wall construction and concrete pouring to continue on Facebook Share Wall construction and concrete pouring to continue on X (formerly Twitter) Share Wall construction and concrete pouring to continue on Linkedin Email Wall construction and concrete pouring to continue link

    This week’s progress:

    • Concrete pouring continued
    • Wall construction began
    • Asphalt patching began along newly curbed areas

    Next week’s activities:

    • Concrete pouring will continue
    • Wall construction will continue

    This week’s progress:

    • Concrete pouring continued
    • Wall construction began
    • Asphalt patching began along newly curbed areas

    Next week’s activities:

    • Concrete pouring will continue
    • Wall construction will continue
  • Storm sewer rehab complete. Concrete pouring next week

    Share Storm sewer rehab complete. Concrete pouring next week on Facebook Share Storm sewer rehab complete. Concrete pouring next week on X (formerly Twitter) Share Storm sewer rehab complete. Concrete pouring next week on Linkedin Email Storm sewer rehab complete. Concrete pouring next week link

    This week’s progress:

    • Storm Sewer rehabilitation complete
    • Concrete pouring began on the north side of Cedar Lake Road

    Next week’s activities:

    • Concrete pouring will continue
    • Asphalt patching will begin along new curb areas

    As part of MnDOT's Cedar Lake Road and Jordan Avenue project, Jordan Avenue S. south of Cedar Lake Road will be closed beginning July 27. Cedar Lake Road will remain open.

    This week’s progress:

    • Storm Sewer rehabilitation complete
    • Concrete pouring began on the north side of Cedar Lake Road

    Next week’s activities:

    • Concrete pouring will continue
    • Asphalt patching will begin along new curb areas

    As part of MnDOT's Cedar Lake Road and Jordan Avenue project, Jordan Avenue S. south of Cedar Lake Road will be closed beginning July 27. Cedar Lake Road will remain open.

  • Work continues on north side of Cedar Lake Road

    Share Work continues on north side of Cedar Lake Road on Facebook Share Work continues on north side of Cedar Lake Road on X (formerly Twitter) Share Work continues on north side of Cedar Lake Road on Linkedin Email Work continues on north side of Cedar Lake Road link

    Last week’s progress:

    • Traffic control shift complete
    • Sawing and pavement removals on the north side of Cedar Lake Road began

    This week’s activities:

    • Storm sewer rehabilitation begins on the north side of Cedar Lake Road
    • Grading for sidewalk and curb and gutter continues

    Please be aware of traffic control changes and watch for shifting traffic patterns.

    Last week’s progress:

    • Traffic control shift complete
    • Sawing and pavement removals on the north side of Cedar Lake Road began

    This week’s activities:

    • Storm sewer rehabilitation begins on the north side of Cedar Lake Road
    • Grading for sidewalk and curb and gutter continues

    Please be aware of traffic control changes and watch for shifting traffic patterns.

  • Traffic shifts coming next week

    Share Traffic shifts coming next week on Facebook Share Traffic shifts coming next week on X (formerly Twitter) Share Traffic shifts coming next week on Linkedin Email Traffic shifts coming next week link

    This week’s progress:

    • Asphalt patching at new curb and gutter complete
    • Grading in for sidewalk on the south side of Cedar Lake Road complete
    • Sidewalk pouring began on the south side of Cedar Lake Road began

    Next week’s activities:

    • Sidewalk pouring will continue
    • Traffic will be shifted from North to South.

    Please be aware of traffic control changes and watch for shifting traffic patterns.

    This week’s progress:

    • Asphalt patching at new curb and gutter complete
    • Grading in for sidewalk on the south side of Cedar Lake Road complete
    • Sidewalk pouring began on the south side of Cedar Lake Road began

    Next week’s activities:

    • Sidewalk pouring will continue
    • Traffic will be shifted from North to South.

    Please be aware of traffic control changes and watch for shifting traffic patterns.

  • Grading and sidewalk pouring next week

    Share Grading and sidewalk pouring next week on Facebook Share Grading and sidewalk pouring next week on X (formerly Twitter) Share Grading and sidewalk pouring next week on Linkedin Email Grading and sidewalk pouring next week link

    This week’s progress:

    • Concrete curb and gutter installed on the south side of Cedar Lake Road

    Next week’s activities:

    • Grading will continue
    • Concrete sidewalk pouring will begin

    This week’s progress:

    • Concrete curb and gutter installed on the south side of Cedar Lake Road

    Next week’s activities:

    • Grading will continue
    • Concrete sidewalk pouring will begin
  • Concrete pouring begins next week

    Share Concrete pouring begins next week on Facebook Share Concrete pouring begins next week on X (formerly Twitter) Share Concrete pouring begins next week on Linkedin Email Concrete pouring begins next week link

    This week's progress included:

    • The completion of storm sewer rehabilitation on the south side of Cedar Lake Road
    • Signal pole removal
    • Grading for pedestrian improvements began

    Next week's activities include:

    • Concrete pouring for curb, gutter and sidewalk

    This week's progress included:

    • The completion of storm sewer rehabilitation on the south side of Cedar Lake Road
    • Signal pole removal
    • Grading for pedestrian improvements began

    Next week's activities include:

    • Concrete pouring for curb, gutter and sidewalk
  • Project update June 12, construction underway

    Share Project update June 12, construction underway on Facebook Share Project update June 12, construction underway on X (formerly Twitter) Share Project update June 12, construction underway on Linkedin Email Project update June 12, construction underway link

    On June 11, the project began with work primarily confined to the south side of Cedar Lake Road.

    This week's progress:

    • Traffic control was installed and traffic was shifted north on Cedar Lake Road
    • Curb and sidewalk removals began
    • Tree removals were completed on the south side of Cedar Lake Road

    Next weeks activities:

    • Removal of curb and sidewalk will continue
    • Storm sewer rehabilitation will begin

    Please be aware of traffic control changes and watch for shifting traffic patterns.

    On June 11, the project began with work primarily confined to the south side of Cedar Lake Road.

    This week's progress:

    • Traffic control was installed and traffic was shifted north on Cedar Lake Road
    • Curb and sidewalk removals began
    • Tree removals were completed on the south side of Cedar Lake Road

    Next weeks activities:

    • Removal of curb and sidewalk will continue
    • Storm sewer rehabilitation will begin

    Please be aware of traffic control changes and watch for shifting traffic patterns.

Page last updated: 21 Aug 2026, 09:23 AM