Storm sewer rehab complete. Concrete pouring next week
This week’s progress:
- Storm Sewer rehabilitation complete
- Concrete pouring began on the north side of Cedar Lake Road
Next week’s activities:
- Concrete pouring will continue
- Asphalt patching will begin along new curb areas
As part of MnDOT's Cedar Lake Road and Jordan Avenue project, Jordan Avenue S. south of Cedar Lake Road will be closed beginning July 27. Cedar Lake Road will remain open.