Sept. 26, Project update
Woodlawn Avenue will be closed at the North Entrance to the Groveland Cemetery beginning Monday Sept. 29. View the detour map. The closure is expected to last two days. This will allow crews to install new storm sewer structures.
This week’s progress:
- Tree removal complete
- Began removal of pavement
Next week’s schedule:
- Install storm sewer on Woodlawn Avenue
- Begin storm sewer installation west of Woodlawn Avenue