Trail grading begins next week
This week’s progress included:
- Wall painting complete
- Relocation of private utilities continues
- Curb and gutter installation continues
- Concrete driveway installation complete
Next week’s activities include:
- Relocation of private utilities will continue
- Grading for trail will begin