Wall construction complete

This week’s progress included:

  • Wall construction complete
  • Grading for curb and trail continued
  • Relocation of private utilities continued

Next week’s activities include:

  • Curb and gutter installation will begin
  • Relocation of private utilities will continue

Please be aware of traffic control changes and watch for changing traffic patterns.