Wall construction to be completed next week
This week’s progress included:
- Wall construction continues
- Pavement removals complete
- Storm sewer installation complete
- Grading for curb and trail has begun
- Relocation of private utilities continues
Next week’s activities include:
- Wall construction will be completed
- Grading for curb and trail will continue
- Relocation of private utilities will continue
Please be aware of traffic control changes and watch for changing traffic patterns.