Work continues on Oakland Road.

  • Crews removed and replaced damaged curb and gutter, as well as added pedestrian ramps
  • Crews completed trail removal
  • During the week of July 20, crews will focus on regrading and paving the trail.
  • Restoration behind the trail and curbs will occur next week.