2026 Overlay project

Share 2026 Overlay project on Facebook Share 2026 Overlay project on X (formerly Twitter) Share 2026 Overlay project on Linkedin Email 2026 Overlay project link

The City of Minnetonka is preparing for the 2026 Overlay Project, which includes improvements on Williston Road, Oakland Road, Minnetonka Drive, Woodland Road and the public works parking lot.

The project includes pavement improvements, trail replacement, damaged curb and gutter replacement, utility casting replacement, and drainage improvements.

Traffic Impacts

During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.

Will I be assessed?

No. The city does not specifically assess for these improvements. These types of improvements are primarily funded through the city's street and utility funds.

Project schedule

Construction will start this summer and is expected to last approximately 4-6 weeks in each location. Detailed information regarding construction phases and schedule updates will be communicated via the project website and email/text updates. Please subscribe for updates to stay informed.

Schedules are weather-dependent and subject to change.

The City of Minnetonka is preparing for the 2026 Overlay Project, which includes improvements on Williston Road, Oakland Road, Minnetonka Drive, Woodland Road and the public works parking lot.

The project includes pavement improvements, trail replacement, damaged curb and gutter replacement, utility casting replacement, and drainage improvements.

Traffic Impacts

During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.

Will I be assessed?

No. The city does not specifically assess for these improvements. These types of improvements are primarily funded through the city's street and utility funds.

Project schedule

Construction will start this summer and is expected to last approximately 4-6 weeks in each location. Detailed information regarding construction phases and schedule updates will be communicated via the project website and email/text updates. Please subscribe for updates to stay informed.

Schedules are weather-dependent and subject to change.

  • Striping underway on Williston Road

    Share Striping underway on Williston Road on Facebook Share Striping underway on Williston Road on X (formerly Twitter) Share Striping underway on Williston Road on Linkedin Email Striping underway on Williston Road link
    • Paving is complete on Williston Road and the Public Works parking lot
    • Striping is underway today, Sept. 4 on Williston Road
    • The final two segments, Minnetonka Drive and Woodland Road, are scheduled for Sept. 14.
    • Paving is complete on Williston Road and the Public Works parking lot
    • Striping is underway today, Sept. 4 on Williston Road
    • The final two segments, Minnetonka Drive and Woodland Road, are scheduled for Sept. 14.
  • Additional patching, paving of Williston next week

    Share Additional patching, paving of Williston next week on Facebook Share Additional patching, paving of Williston next week on X (formerly Twitter) Share Additional patching, paving of Williston next week on Linkedin Email Additional patching, paving of Williston next week link
    • After milling Williston Road, several areas were identified for additional patching which will occur Monday, Aug. 31.
    • Paving on Williston is scheduled for Tuesday, Sept. 1.
    • Please be aware of traffic delays next Monday and Tuesday as flaggers will be used to direct traffic.
    • The Public Works parking lot was milled and is scheduled for paving Monday, Aug. 31.
    • After milling Williston Road, several areas were identified for additional patching which will occur Monday, Aug. 31.
    • Paving on Williston is scheduled for Tuesday, Sept. 1.
    • Please be aware of traffic delays next Monday and Tuesday as flaggers will be used to direct traffic.
    • The Public Works parking lot was milled and is scheduled for paving Monday, Aug. 31.
  • Crews to mill Williston this weekend

    Share Crews to mill Williston this weekend on Facebook Share Crews to mill Williston this weekend on X (formerly Twitter) Share Crews to mill Williston this weekend on Linkedin Email Crews to mill Williston this weekend link
    • Crews completed gutter and sidewalk replacement at the Civic Center and Public Works parking lot.
    • Damaged areas, including electrical and irrigation, are being repaired
    • On Saturday, Aug. 22, crews will mill Williston Road.
    • Paving will occur the week of Aug. 24.
    • Crews completed gutter and sidewalk replacement at the Civic Center and Public Works parking lot.
    • Damaged areas, including electrical and irrigation, are being repaired
    • On Saturday, Aug. 22, crews will mill Williston Road.
    • Paving will occur the week of Aug. 24.
  • Williston Road work underway

    Share Williston Road work underway on Facebook Share Williston Road work underway on X (formerly Twitter) Share Williston Road work underway on Linkedin Email Williston Road work underway link

    Williston Road

    • Crews removed damaged curb and gutter. Replacement is underway.
    • Concrete work and patching will continue the week of Aug. 17.

    Public Works parking lot

    • Crews removed and replaced damaged curb and gutter this week.
    • Areas adjacent to the replaced curb will be backfilled and patched the week of Aug. 17.

    Williston Road

    • Crews removed damaged curb and gutter. Replacement is underway.
    • Concrete work and patching will continue the week of Aug. 17.

    Public Works parking lot

    • Crews removed and replaced damaged curb and gutter this week.
    • Areas adjacent to the replaced curb will be backfilled and patched the week of Aug. 17.
  • Operations move to Williston Road

    Share Operations move to Williston Road on Facebook Share Operations move to Williston Road on X (formerly Twitter) Share Operations move to Williston Road on Linkedin Email Operations move to Williston Road link

    Oakland Road progress

    • Striping crews will complete work on Oakland Road today, applying roadway markings and crosswalks

    Williston Road progress

    • Crews will move to Williston Road on Wednesday, Aug. 12 adjacent to City Hall and Ice Arenas A and B
    • Pedestrian ramps as well as concrete curb and gutter removals are underway
    • Traffic will be flagged and access will be maintained, but drivers should expect delays
    • Please follow flagger instructions and watch for changing traffic control

    Public Works parking lot

    • Improvements are coming to the Public Works parking lot
    • Most work will occur after hours

    Oakland Road progress

    • Striping crews will complete work on Oakland Road today, applying roadway markings and crosswalks

    Williston Road progress

    • Crews will move to Williston Road on Wednesday, Aug. 12 adjacent to City Hall and Ice Arenas A and B
    • Pedestrian ramps as well as concrete curb and gutter removals are underway
    • Traffic will be flagged and access will be maintained, but drivers should expect delays
    • Please follow flagger instructions and watch for changing traffic control

    Public Works parking lot

    • Improvements are coming to the Public Works parking lot
    • Most work will occur after hours
  • Paving operations next week

    Share Paving operations next week on Facebook Share Paving operations next week on X (formerly Twitter) Share Paving operations next week on Linkedin Email Paving operations next week link

    This week, crews milled the roadway and adjusted manholes. Paving operations are scheduled for Monday, Aug. 3, and are expected to be completed in a day.

    Roadway striping will follow paving next week.

    Watch for traffic flagging, lots of large trucks and machinery as well as changing traffic control beginning Aug. 3.

    This week, crews milled the roadway and adjusted manholes. Paving operations are scheduled for Monday, Aug. 3, and are expected to be completed in a day.

    Roadway striping will follow paving next week.

    Watch for traffic flagging, lots of large trucks and machinery as well as changing traffic control beginning Aug. 3.

  • Roadway milling on Oakland Road next week

    Share Roadway milling on Oakland Road next week on Facebook Share Roadway milling on Oakland Road next week on X (formerly Twitter) Share Roadway milling on Oakland Road next week on Linkedin Email Roadway milling on Oakland Road next week link

    Crews completed trail paving and restoration along Oakland Road last week.

    Beginning Monday, July 27, crews will mill the roadway. This is expected to last two days. Following milling, crews will adjust manholes.

    Please drive carefully and be aware of changing traffic control.

    Crews completed trail paving and restoration along Oakland Road last week.

    Beginning Monday, July 27, crews will mill the roadway. This is expected to last two days. Following milling, crews will adjust manholes.

    Please drive carefully and be aware of changing traffic control.

  • Trail paving and restoration next week

    Share Trail paving and restoration next week on Facebook Share Trail paving and restoration next week on X (formerly Twitter) Share Trail paving and restoration next week on Linkedin Email Trail paving and restoration next week link

    Work continues on Oakland Road.

    • Crews removed and replaced damaged curb and gutter, as well as added pedestrian ramps
    • Crews completed trail removal
    • During the week of July 20, crews will focus on regrading and paving the trail.
    • Restoration behind the trail and curbs will occur next week.

    Work continues on Oakland Road.

    • Crews removed and replaced damaged curb and gutter, as well as added pedestrian ramps
    • Crews completed trail removal
    • During the week of July 20, crews will focus on regrading and paving the trail.
    • Restoration behind the trail and curbs will occur next week.
  • Project kicks off next week on Oakland Road

    Share Project kicks off next week on Oakland Road on Facebook Share Project kicks off next week on Oakland Road on X (formerly Twitter) Share Project kicks off next week on Oakland Road on Linkedin Email Project kicks off next week on Oakland Road link

    Crews will begin work on Oakland Road on Monday, July 13. Work will include

    • Miscellaneous curb and gutter removal and replacement
    • Removal of trail, and trail replacement
    • Milling and overlay of the roadway.

    Oakland road will remain open to traffic for the duration of the project. Please slow down, and be cautious of workers and alert of traffic control changes.

    Crews will begin work on Oakland Road on Monday, July 13. Work will include

    • Miscellaneous curb and gutter removal and replacement
    • Removal of trail, and trail replacement
    • Milling and overlay of the roadway.

    Oakland road will remain open to traffic for the duration of the project. Please slow down, and be cautious of workers and alert of traffic control changes.