The City of Minnetonka is preparing for the 2026 Overlay Project, which includes improvements on Williston Road, Oakland Road, Minnetonka Drive, Woodland Road and the public works parking lot.
The project includes pavement improvements, trail replacement, damaged curb and gutter replacement, utility casting replacement, and drainage improvements.
Traffic Impacts
During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.
Will I be assessed?
No. The city does not specifically assess for these improvements. These types of improvements are primarily funded through the city's street and utility funds.
Project schedule
Construction will start this summer and is expected to last approximately 4-6 weeks in each location. Detailed information regarding construction phases and schedule updates will be communicated via the project website and email/text updates. Please subscribe for updates to stay informed.
Schedules are weather-dependent and subject to change.
The City of Minnetonka is preparing for the 2026 Overlay Project, which includes improvements on Williston Road, Oakland Road, Minnetonka Drive, Woodland Road and the public works parking lot.
The project includes pavement improvements, trail replacement, damaged curb and gutter replacement, utility casting replacement, and drainage improvements.
Traffic Impacts
During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.
Will I be assessed?
No. The city does not specifically assess for these improvements. These types of improvements are primarily funded through the city's street and utility funds.
Project schedule
Construction will start this summer and is expected to last approximately 4-6 weeks in each location. Detailed information regarding construction phases and schedule updates will be communicated via the project website and email/text updates. Please subscribe for updates to stay informed.
Schedules are weather-dependent and subject to change.
Share Roadway milling on Oakland Road next week on FacebookShare Roadway milling on Oakland Road next week on X (formerly Twitter)Share Roadway milling on Oakland Road next week on LinkedinEmail Roadway milling on Oakland Road next week link
Crews completed trail paving and restoration along Oakland Road last week.
Beginning Monday, July 27, crews will mill the roadway. This is expected to last two days. Following milling, crews will adjust manholes.
Please drive carefully and be aware of changing traffic control.
Crews completed trail paving and restoration along Oakland Road last week.
Beginning Monday, July 27, crews will mill the roadway. This is expected to last two days. Following milling, crews will adjust manholes.
Please drive carefully and be aware of changing traffic control.
Share Trail paving and restoration next week on FacebookShare Trail paving and restoration next week on X (formerly Twitter)Share Trail paving and restoration next week on LinkedinEmail Trail paving and restoration next week link
Work continues on Oakland Road.
Crews removed and replaced damaged curb and gutter, as well as added pedestrian ramps
Crews completed trail removal
During the week of July 20, crews will focus on regrading and paving the trail.
Restoration behind the trail and curbs will occur next week.
Work continues on Oakland Road.
Crews removed and replaced damaged curb and gutter, as well as added pedestrian ramps
Crews completed trail removal
During the week of July 20, crews will focus on regrading and paving the trail.
Restoration behind the trail and curbs will occur next week.
Share Project kicks off next week on Oakland Road on FacebookShare Project kicks off next week on Oakland Road on X (formerly Twitter)Share Project kicks off next week on Oakland Road on LinkedinEmail Project kicks off next week on Oakland Road link
Crews will begin work on Oakland Road on Monday, July 13. Work will include
Miscellaneous curb and gutter removal and replacement
Removal of trail, and trail replacement
Milling and overlay of the roadway.
Oakland road will remain open to traffic for the duration of the project. Please slow down, and be cautious of workers and alert of traffic control changes.
Crews will begin work on Oakland Road on Monday, July 13. Work will include
Miscellaneous curb and gutter removal and replacement
Removal of trail, and trail replacement
Milling and overlay of the roadway.
Oakland road will remain open to traffic for the duration of the project. Please slow down, and be cautious of workers and alert of traffic control changes.