The City of Minnetonka is preparing for street improvements along Ridgedale Drive from Cartway Lane to Plymouth Road (County Road 61) and Cartway Lane from Ridgedale Drive to Plymouth Road (County Road 61).

The project includes improvements to the pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.

Traffic Impacts

During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures, and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.

Project Schedule

Construction will begin in mid-September and last until late October. Detailed information regarding construction phases and schedule updates

will be communicated via this page and email/text updates. Please subscribe for updates to stay informed. Schedules are weather dependent and subject to change.

Will I be assessed

No, property owners will not be assessed. These improvements are funded through the city’s Street Improvement Fund.

How to stay informed

  • Subscribe to receive email notifications by clicking "Follow project" on the this page.
  • Text “RIDGEDALE-DRIVE” to 1-888-698-1850 to subscribe to text updates.
  • Contact our staff to learn more or ask questions.

The City of Minnetonka is preparing for street improvements along Ridgedale Drive from Cartway Lane to Plymouth Road (County Road 61) and Cartway Lane from Ridgedale Drive to Plymouth Road (County Road 61).

The project includes improvements to the pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.

Traffic Impacts

During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures, and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.

Project Schedule

Construction will begin in mid-September and last until late October. Detailed information regarding construction phases and schedule updates

will be communicated via this page and email/text updates. Please subscribe for updates to stay informed. Schedules are weather dependent and subject to change.

Will I be assessed

No, property owners will not be assessed. These improvements are funded through the city’s Street Improvement Fund.

How to stay informed

  • Subscribe to receive email notifications by clicking "Follow project" on the this page.
  • Text “RIDGEDALE-DRIVE” to 1-888-698-1850 to subscribe to text updates.
  • Contact our staff to learn more or ask questions.
  • Construction begins Sept. 21

    Share Construction begins Sept. 21 on Facebook Share Construction begins Sept. 21 on X (formerly Twitter) Share Construction begins Sept. 21 on Linkedin Email Construction begins Sept. 21 link

    Work on the Ridgedale Drive/Cartway Lane project is set to begin on Monday, Sept. 21. The intersection at Ridgedale Drive and Cartway Lane will have several partial closures.

    Improvements include:

    • Mill and overlay
    • Repairs to damaged curb and sidewalks
    • New pedestrian ramps
    • New utility castings
    • Improved traffic signals
    • Updated pavement markings

    The project is expected to be complete by mid-October.

    Work on the Ridgedale Drive/Cartway Lane project is set to begin on Monday, Sept. 21. The intersection at Ridgedale Drive and Cartway Lane will have several partial closures.

    Improvements include:

    • Mill and overlay
    • Repairs to damaged curb and sidewalks
    • New pedestrian ramps
    • New utility castings
    • Improved traffic signals
    • Updated pavement markings

    The project is expected to be complete by mid-October.

  • Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects

    Share Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects on Facebook Share Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects on X (formerly Twitter) Share Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects on Linkedin Email Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects link

    Minnetonka City Council will consider awarding contracts for the Cedar Lake Road and Ridgedale Drive projects at its April 27 meeting. The meeting will be held at 6 p.m. in the City Council Chambers located at 14600 Minnetonka Blvd.

    Although these projects are in different areas of the city, they will be completed under one contract, as the work is similar in both locations

    Minnetonka City Council will consider awarding contracts for the Cedar Lake Road and Ridgedale Drive projects at its April 27 meeting. The meeting will be held at 6 p.m. in the City Council Chambers located at 14600 Minnetonka Blvd.

    Although these projects are in different areas of the city, they will be completed under one contract, as the work is similar in both locations

  • Council to consider Cedar Lake Road and Ridgedale Drive projects

    Share Council to consider Cedar Lake Road and Ridgedale Drive projects on Facebook Share Council to consider Cedar Lake Road and Ridgedale Drive projects on X (formerly Twitter) Share Council to consider Cedar Lake Road and Ridgedale Drive projects on Linkedin Email Council to consider Cedar Lake Road and Ridgedale Drive projects link

    City Council will be asked to authorize projects located at Ridgedale Drive and Cedar Lake Road, during its March 23 meeting. Although these projects are in different areas of the city, they will be bided as a single project.

    Council will consider pavement improvements and signal replacement as part of this project.

    The meeting will be held on Monday, March 23 at 6 p.m. in the second floor Council Chambers at 14600 Minnetonka Blvd.

    City Council will be asked to authorize projects located at Ridgedale Drive and Cedar Lake Road, during its March 23 meeting. Although these projects are in different areas of the city, they will be bided as a single project.

    Council will consider pavement improvements and signal replacement as part of this project.

    The meeting will be held on Monday, March 23 at 6 p.m. in the second floor Council Chambers at 14600 Minnetonka Blvd.

  • Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday

    Share Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday on Facebook Share Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday on X (formerly Twitter) Share Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday on Linkedin Email Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday link

    City Council will be asked to approve a resolution that would authorize work on Cedar Lake Road and Ridgedale Drive in 2026.The resolution includes the feasibility report, authorization of plans and specifications and authorizes the acquisition of easements in the project areas.

    Although these projects are in different neighborhoods of the city, the scope of work is similar. These projects will be bid as a single contract.

    The meeting will be held at 6 p.m. at 14600 Minnetonka Blvd in the second-floor Council Chambers.

    City Council will be asked to approve a resolution that would authorize work on Cedar Lake Road and Ridgedale Drive in 2026.The resolution includes the feasibility report, authorization of plans and specifications and authorizes the acquisition of easements in the project areas.

    Although these projects are in different neighborhoods of the city, the scope of work is similar. These projects will be bid as a single contract.

    The meeting will be held at 6 p.m. at 14600 Minnetonka Blvd in the second-floor Council Chambers.

  • Aug. 1 project update

    Share Aug. 1 project update on Facebook Share Aug. 1 project update on X (formerly Twitter) Share Aug. 1 project update on Linkedin Email Aug. 1 project update link

    The engineering division will host an open house regarding the Ridgedale Drive/Cartway Lane improvements project on Thursday, Aug. 14 at 5 p.m. at the Minnetonka Community Center. Staff will be present to answer questions and explain the details of the project. If you cannot attend the meeting, contact Engineering Project Manager Mitch Hatcher by phone or email. Presentations from the meeting will be available on this website.

    Ridgedale Drive/Cartway Lane project proposal

    • Improvements to pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.
    • Construction is planned for 2026

    The engineering division will host an open house regarding the Ridgedale Drive/Cartway Lane improvements project on Thursday, Aug. 14 at 5 p.m. at the Minnetonka Community Center. Staff will be present to answer questions and explain the details of the project. If you cannot attend the meeting, contact Engineering Project Manager Mitch Hatcher by phone or email. Presentations from the meeting will be available on this website.

    Ridgedale Drive/Cartway Lane project proposal

    • Improvements to pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.
    • Construction is planned for 2026
Page last updated: 18 Sep 2026, 02:17 PM