Ridgedale Drive/Cartway Lane Improvement project
The City of Minnetonka is preparing for street improvements along Ridgedale Drive from Cartway Lane to Plymouth Road (County Road 61) and Cartway Lane from Ridgedale Drive to Plymouth Road (County Road 61).
The project includes improvements to the pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.
Traffic Impacts
During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures, and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.
Project Schedule
Construction will begin in mid-September and last until late October. Detailed information regarding construction phases and schedule updates
will be communicated via this page and email/text updates. Please subscribe for updates to stay informed. Schedules are weather dependent and subject to change.
Will I be assessed
No, property owners will not be assessed. These improvements are funded through the city’s Street Improvement Fund.
How to stay informed
- Subscribe to receive email notifications by clicking "Follow project" on the this page.
- Text “RIDGEDALE-DRIVE” to 1-888-698-1850 to subscribe to text updates.
- Contact our staff to learn more or ask questions.
The City of Minnetonka is preparing for street improvements along Ridgedale Drive from Cartway Lane to Plymouth Road (County Road 61) and Cartway Lane from Ridgedale Drive to Plymouth Road (County Road 61).
The project includes improvements to the pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.
Traffic Impacts
During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures, and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.
Project Schedule
Construction will begin in mid-September and last until late October. Detailed information regarding construction phases and schedule updates
will be communicated via this page and email/text updates. Please subscribe for updates to stay informed. Schedules are weather dependent and subject to change.
Will I be assessed
No, property owners will not be assessed. These improvements are funded through the city’s Street Improvement Fund.
How to stay informed
- Subscribe to receive email notifications by clicking "Follow project" on the this page.
- Text “RIDGEDALE-DRIVE” to 1-888-698-1850 to subscribe to text updates.
- Contact our staff to learn more or ask questions.
-
Signal installation complete
Share Signal installation complete on Facebook Share Signal installation complete on X (formerly Twitter) Share Signal installation complete on Linkedin Email Signal installation complete linkThis week’s progress included:
- Asphalt patching complete
- Signal system installation complete
- Brick paver installation began
- Signage installation began
- Turf restoration began
Next week’s activities include:
- Milling roadway
- Asphalt paving
- Roadway striping
This week’s progress included:
- Asphalt patching complete
- Signal system installation complete
- Brick paver installation began
- Signage installation began
- Turf restoration began
Next week’s activities include:
- Milling roadway
- Asphalt paving
- Roadway striping
-
Curb and gutter installation complete
Share Curb and gutter installation complete on Facebook Share Curb and gutter installation complete on X (formerly Twitter) Share Curb and gutter installation complete on Linkedin Email Curb and gutter installation complete linkThis week’s progress included:
- Curb and gutter installation complete
- Sidewalk installation complete
- Traffic signal system construction began
Next week’s activities include:
- Asphalt paving begins
- Traffic signal system construction continues
This week’s progress included:
- Curb and gutter installation complete
- Sidewalk installation complete
- Traffic signal system construction began
Next week’s activities include:
- Asphalt paving begins
- Traffic signal system construction continues
-
Traffic control in place. Concrete work next week
Share Traffic control in place. Concrete work next week on Facebook Share Traffic control in place. Concrete work next week on X (formerly Twitter) Share Traffic control in place. Concrete work next week on Linkedin Email Traffic control in place. Concrete work next week linkThis week’s progress included:
- Traffic control change and lane closures began
- Traffic signal system removed
- Storm sewer installation complete
Next week’s activities include:
- Concrete work will begin
- New traffic signal installation begins
This week’s progress included:
- Traffic control change and lane closures began
- Traffic signal system removed
- Storm sewer installation complete
Next week’s activities include:
- Concrete work will begin
- New traffic signal installation begins
-
Construction begins Sept. 21
Share Construction begins Sept. 21 on Facebook Share Construction begins Sept. 21 on X (formerly Twitter) Share Construction begins Sept. 21 on Linkedin Email Construction begins Sept. 21 linkWork on the Ridgedale Drive/Cartway Lane project is set to begin on Monday, Sept. 21. The intersection at Ridgedale Drive and Cartway Lane will have several partial closures.
Improvements include:
- Mill and overlay
- Repairs to damaged curb and sidewalks
- New pedestrian ramps
- New utility castings
- Improved traffic signals
- Updated pavement markings
The project is expected to be complete by mid-October.
Work on the Ridgedale Drive/Cartway Lane project is set to begin on Monday, Sept. 21. The intersection at Ridgedale Drive and Cartway Lane will have several partial closures.
Improvements include:
- Mill and overlay
- Repairs to damaged curb and sidewalks
- New pedestrian ramps
- New utility castings
- Improved traffic signals
- Updated pavement markings
The project is expected to be complete by mid-October.
-
Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects
Share Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects on Facebook Share Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects on X (formerly Twitter) Share Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects on Linkedin Email Council to consider awarding contract for Ridgedale Drive/Cedar Lake Road projects linkMinnetonka City Council will consider awarding contracts for the Cedar Lake Road and Ridgedale Drive projects at its April 27 meeting. The meeting will be held at 6 p.m. in the City Council Chambers located at 14600 Minnetonka Blvd.
Although these projects are in different areas of the city, they will be completed under one contract, as the work is similar in both locations
Minnetonka City Council will consider awarding contracts for the Cedar Lake Road and Ridgedale Drive projects at its April 27 meeting. The meeting will be held at 6 p.m. in the City Council Chambers located at 14600 Minnetonka Blvd.
Although these projects are in different areas of the city, they will be completed under one contract, as the work is similar in both locations
-
Council to consider Cedar Lake Road and Ridgedale Drive projects
Share Council to consider Cedar Lake Road and Ridgedale Drive projects on Facebook Share Council to consider Cedar Lake Road and Ridgedale Drive projects on X (formerly Twitter) Share Council to consider Cedar Lake Road and Ridgedale Drive projects on Linkedin Email Council to consider Cedar Lake Road and Ridgedale Drive projects linkCity Council will be asked to authorize projects located at Ridgedale Drive and Cedar Lake Road, during its March 23 meeting. Although these projects are in different areas of the city, they will be bided as a single project.
Council will consider pavement improvements and signal replacement as part of this project.
The meeting will be held on Monday, March 23 at 6 p.m. in the second floor Council Chambers at 14600 Minnetonka Blvd.
City Council will be asked to authorize projects located at Ridgedale Drive and Cedar Lake Road, during its March 23 meeting. Although these projects are in different areas of the city, they will be bided as a single project.
Council will consider pavement improvements and signal replacement as part of this project.
The meeting will be held on Monday, March 23 at 6 p.m. in the second floor Council Chambers at 14600 Minnetonka Blvd.
-
Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday
Share Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday on Facebook Share Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday on X (formerly Twitter) Share Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday on Linkedin Email Council asked to approve Cedar Lake Road and Ridgedale Drive projects Monday linkCity Council will be asked to approve a resolution that would authorize work on Cedar Lake Road and Ridgedale Drive in 2026.The resolution includes the feasibility report, authorization of plans and specifications and authorizes the acquisition of easements in the project areas.
Although these projects are in different neighborhoods of the city, the scope of work is similar. These projects will be bid as a single contract.
The meeting will be held at 6 p.m. at 14600 Minnetonka Blvd in the second-floor Council Chambers.
City Council will be asked to approve a resolution that would authorize work on Cedar Lake Road and Ridgedale Drive in 2026.The resolution includes the feasibility report, authorization of plans and specifications and authorizes the acquisition of easements in the project areas.
Although these projects are in different neighborhoods of the city, the scope of work is similar. These projects will be bid as a single contract.
The meeting will be held at 6 p.m. at 14600 Minnetonka Blvd in the second-floor Council Chambers.
-
Aug. 1 project update
Share Aug. 1 project update on Facebook Share Aug. 1 project update on X (formerly Twitter) Share Aug. 1 project update on Linkedin Email Aug. 1 project update linkThe engineering division will host an open house regarding the Ridgedale Drive/Cartway Lane improvements project on Thursday, Aug. 14 at 5 p.m. at the Minnetonka Community Center. Staff will be present to answer questions and explain the details of the project. If you cannot attend the meeting, contact Engineering Project Manager Mitch Hatcher by phone or email. Presentations from the meeting will be available on this website.
Ridgedale Drive/Cartway Lane project proposal
- Improvements to pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.
- Construction is planned for 2026
The engineering division will host an open house regarding the Ridgedale Drive/Cartway Lane improvements project on Thursday, Aug. 14 at 5 p.m. at the Minnetonka Community Center. Staff will be present to answer questions and explain the details of the project. If you cannot attend the meeting, contact Engineering Project Manager Mitch Hatcher by phone or email. Presentations from the meeting will be available on this website.
Ridgedale Drive/Cartway Lane project proposal
- Improvements to pavement, curb, sidewalks, pedestrian ramps, utility castings, traffic signals, signs and pavement markings.
- Construction is planned for 2026
-
Phone 952-939-8230 Email ajsoland@minnetonkamn.gov -
Engineering Project Manager
-
City Engineer
Phone 952-939-8239 Email polson@minnetonkamn.gov
-
Data collection and surveying- Summer 2025
Ridgedale Drive/Cartway Lane Improvement project has finished this stageStaff and consultants will collect data including vehicle, pedestrian and bicycle counts.
Once complete, staff will begin working on a preliminary design. -
Informational open house- Summer 2025
Ridgedale Drive/Cartway Lane Improvement project has finished this stageStaff held an informational open house on Aug. 14 at the Minnetonka Community Center.
-
Council Approval
Ridgedale Drive/Cartway Lane Improvement project is currently at this stageCouncil will be asked to approve the project at its Dec. 8 meeting.
-
Construction begins- 2026
this is an upcoming stage for Ridgedale Drive/Cartway Lane Improvement project