Pavement restoration scheduled this week

Work on the project continues this week.

  • Crews finished installing storm sewer structures and pipes, graded and restored disturbed areas with topsoil and seed.
  • Crews will continue watering and maintaining seeded areas this week.
  • Street pavement and curbing around the new drainage structure will be restored this week.
  • Expect to see construction activity and traffic control on Scenic Lane South, along with temporary lane closures. Access for residents will be maintained around the construction activity.