May 30, project update

Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.

This week’s progress:

  • Completed utility locating
  • Installed sanitary sewer pipe

Next week’s activities include:

  • Pipe testing
  • Complete pipe connections
  • Prepare roadway for pavement patching