Sherwood Force Main Replacement project

The Sherwood Force Main Replacement project will provide improvements to the sanitary sewer system along Hopkins Crossroad between Timberline Road and Live Oak Drive. Construction began May 2025 and be completed July 2025.
See project updates, including closures, below. Subscribe for updates to stay informed.
The Sherwood Force Main Replacement project will provide improvements to the sanitary sewer system along Hopkins Crossroad between Timberline Road and Live Oak Drive. Construction began May 2025 and be completed July 2025.
See project updates, including closures, below. Subscribe for updates to stay informed.
-
Timberline Road closure at Hopkins Crossroad
Share Timberline Road closure at Hopkins Crossroad on Facebook Share Timberline Road closure at Hopkins Crossroad on Twitter Share Timberline Road closure at Hopkins Crossroad on Linkedin Email Timberline Road closure at Hopkins Crossroad linkTimberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.
-
June 6, project update
Share June 6, project update on Facebook Share June 6, project update on Twitter Share June 6, project update on Linkedin Email June 6, project update linkLive Oak Drive Closure
Live Oak Drive will open today, Friday, June 6. Thank you for your patience.
This week’s progress:
- Pipe passed all testing
- Pipe connections were made
- Roadway prepared for pavement
Next week’s activities include:
- Curb and gutter patching
- Pavement patching
Please be aware of traffic control changes and watch for changing traffic patterns.
-
May 30, project update
Share May 30, project update on Facebook Share May 30, project update on Twitter Share May 30, project update on Linkedin Email May 30, project update linkLive Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.
This week’s progress:
- Completed utility locating
- Installed sanitary sewer pipe
Next week’s activities include:
- Pipe testing
- Complete pipe connections
- Prepare roadway for pavement patching
-
May 23 Update: Live Oak Drive closure extended
Share May 23 Update: Live Oak Drive closure extended on Facebook Share May 23 Update: Live Oak Drive closure extended on Twitter Share May 23 Update: Live Oak Drive closure extended on Linkedin Email May 23 Update: Live Oak Drive closure extended linkDue to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.
Please use Timberline Road to access the Sherwood Forest Neighborhood.
Next week, crews will:
- Locate existing utilities
- Install sanitary sewer pipe
- Install water main pipe
Please be aware of traffic control changes and watch for changing traffic patterns.
-
May 16, project update
Share May 16, project update on Facebook Share May 16, project update on Twitter Share May 16, project update on Linkedin Email May 16, project update linkLive Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.
This week:
- Traffic control in place
- Pavement removals began
- Construction materials arrived on site
- Sanitary sewer pipe fused
Next week's activities include
- Installing sanitary sewer pipe
- Installing water main pipe
Please watch for traffic control changes and shifting traffic patterns
-
May 9 project update
Share May 9 project update on Facebook Share May 9 project update on Twitter Share May 9 project update on Linkedin Email May 9 project update linkWork will begin on the Sherwood Force Main Replacement project beginning on May 12.
Activities will include:
- Traffic control changes
- Pavement removal
- Importing materials
- Fusing sanitary sewer pipe
- Installing sanitary sewer pipe.
Please watch for traffic control changes and shifting traffic patterns.
Project contacts
-
Phone 952-939-8230 Email ajsoland@minnetonkamn.gov -
Phone 952-988-8410 Email mkuno@minnetonkamn.gov