Live Oak Drive Closure
Live Oak Drive will open today, Friday, June 6. Thank you for your patience.
This week’s progress:
- Pipe passed all testing
- Pipe connections were made
- Roadway prepared for pavement
Next week’s activities include:
- Curb and gutter patching
- Pavement patching
Please be aware of traffic control changes and watch for changing traffic patterns.
Share May 30, project update on Facebook
Share May 30, project update on Linkedin
Email May 30, project update link
Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.
This week’s progress:
- Completed utility locating
- Installed sanitary sewer pipe
Next week’s activities include:
- Pipe testing
- Complete pipe connections
- Prepare roadway for pavement patching
Share May 23 Update: Live Oak Drive closure extended on Facebook
Share May 23 Update: Live Oak Drive closure extended on Linkedin
Email May 23 Update: Live Oak Drive closure extended link
Due to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.
Please use Timberline Road to access the Sherwood Forest Neighborhood.
Next week, crews will:
- Locate existing utilities
- Install sanitary sewer pipe
- Install water main pipe
Please be aware of traffic control changes and watch for changing traffic patterns.
Share May 16, project update on Facebook
Share May 16, project update on Linkedin
Email May 16, project update link
Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.
This week:
- Traffic control in place
- Pavement removals began
- Construction materials arrived on site
- Sanitary sewer pipe fused
Next week's activities include
- Installing sanitary sewer pipe
- Installing water main pipe
Please watch for traffic control changes and shifting traffic patterns
Share May 9 project update on Facebook
Share May 9 project update on Linkedin
Email May 9 project update link
Work will begin on the Sherwood Force Main Replacement project beginning on May 12.
Activities will include:
- Traffic control changes
- Pavement removal
- Importing materials
- Fusing sanitary sewer pipe
- Installing sanitary sewer pipe.
Please watch for traffic control changes and shifting traffic patterns.