This week’s progress included:
- The Live Oak Drive road closure and detour were installed
- Temporary bypass was prepared
- Utility locating began
- Excavation for lining pits began
- Hydrant installation
Next week’s activities include:
- Connection of temporary bypass
- Excavation for lining pits will continue