Share June 11, Oakland Road now open on Facebook
Share June 11, Oakland Road now open on Linkedin
Email June 11, Oakland Road now open link
Oakland Road is now open to traffic in both directions. Thank you for your patience
Share June 6, project update on Facebook
Share June 6, project update on Linkedin
Email June 6, project update link
Oakland Road closure
Oakland Road is scheduled to reopen by Friday, June 13. Thank you for your patience.
This week’s progress:
- Concrete curb patching complete
- Pavement patching today
Next week’s activities include:
- Topsoil and seed placement
- Manhole lining
Share May 30, project update on Facebook
Share May 30, project update on Linkedin
Email May 30, project update link
This week’s progress:
- Manhole installation complete
- Lift station connection complete
Next week’s activities include:
- Concrete curbing
- Asphalt patching
- Topsoil and seed placement
Share May 23, project update on Facebook
Share May 23, project update on Linkedin
Email May 23, project update link
This week, crews installed sanitary sewer pipe and began installing manholes. Next week's work includes:
- Installing remaining manholes
- Making connection to lift station
Share May 16, project update on Facebook
Share May 16, project update on Linkedin
Email May 16, project update link
This week’s progress:
- Traffic control and detour in place
- Pavement removals began
- Construction materials arrived on site
- Sanitary pipe fused
- Sanitary sewer pipe installation began
Next week’s activities include:
- Installing sanitary sewer pipe
- Installing manholes
Share May 9, project update on Facebook
Share May 9, project update on Linkedin
Email May 9, project update link
The city's contractor will begin work on the Brightwood Force Main replacement project on Monday, May 12.
Oakland Road will be closed to through traffic beginning May 12. This closure is expected to last 6 to 8 weeks.
Construction activities next week include:
- Traffic control changes
- Pavement removal
- Importing materials
- Fusing sanitary sewer pipe
- Installing sanitary sewer pipe
Please be aware of traffic control changes and shifting traffic patterns.
Share May 2 project update on Facebook
Share May 2 project update on Linkedin
Email May 2 project update link