Libbs Lake Bridge
The City of Minnetonka is preparing design work for the Libb’s Lake Bridge Replacement Project located over the channel between Libb’s Lake and Gray’s Bay.
This bridge was originally constructed in 1969 and is reaching the end of its service life. This project includes the replacement of the bridge, roadway and associated utilities.
Preliminary design has begun for the bridge replacement. Completion of the design is planned for the end of 2026, at which time the City of Minnetonka will apply for state funding.
Will I be assessed for this project?
No. The City of Minnetonka does not assess for these improvements. The project will be funded through the city’s Street Improvement Fund and/or potential state grant funding.
We want your feedback
As part of the preliminary design, we are interested in residents providing feedback to help plan for the improvements. Please complete this short survey.
The City of Minnetonka is preparing design work for the Libb’s Lake Bridge Replacement Project located over the channel between Libb’s Lake and Gray’s Bay.
This bridge was originally constructed in 1969 and is reaching the end of its service life. This project includes the replacement of the bridge, roadway and associated utilities.
Preliminary design has begun for the bridge replacement. Completion of the design is planned for the end of 2026, at which time the City of Minnetonka will apply for state funding.
Will I be assessed for this project?
No. The City of Minnetonka does not assess for these improvements. The project will be funded through the city’s Street Improvement Fund and/or potential state grant funding.
We want your feedback
As part of the preliminary design, we are interested in residents providing feedback to help plan for the improvements. Please complete this short survey.
-
Libbs Lake Bridge Aesthetics focus group
Share Libbs Lake Bridge Aesthetics focus group on Facebook Share Libbs Lake Bridge Aesthetics focus group on X (formerly Twitter) Share Libbs Lake Bridge Aesthetics focus group on Linkedin Email Libbs Lake Bridge Aesthetics focus group linkThe city is seeking resident feedback through a focus group to help shape the design and community identity of the future Libbs Lake bridge. The focus group will serve in an advisory role to the design team, to explore and shape design features such as railings, architectural details, and colors, along with features visible to people passing under the bridge.
The focus group is limited to approximately 10 people, and will meet twice in-person at the Community Center. The first meeting is planned for Aug. 26.
Interested residents must request to be considered by Aug. 14. Send a message to engineering@minnetonkamn.gov for consideration.
The city is seeking resident feedback through a focus group to help shape the design and community identity of the future Libbs Lake bridge. The focus group will serve in an advisory role to the design team, to explore and shape design features such as railings, architectural details, and colors, along with features visible to people passing under the bridge.
The focus group is limited to approximately 10 people, and will meet twice in-person at the Community Center. The first meeting is planned for Aug. 26.
Interested residents must request to be considered by Aug. 14. Send a message to engineering@minnetonkamn.gov for consideration.
-
Libbs Lake Bridge project to go before council tonight
Share Libbs Lake Bridge project to go before council tonight on Facebook Share Libbs Lake Bridge project to go before council tonight on X (formerly Twitter) Share Libbs Lake Bridge project to go before council tonight on Linkedin Email Libbs Lake Bridge project to go before council tonight linkMinnetonka City Council will be asked to approve the concept plan, authorize improvements and acquire easements for the construction of the Libbs Lake Bridge at tonight's meeting. The resolution will also ask to form a bridge aesthetics focus group to help determine the future bridge's appearance. Council meetings are held at 6 p.m. located at 14600 Minnetonka Blvd in the second-floor Council Chambers.
Minnetonka City Council will be asked to approve the concept plan, authorize improvements and acquire easements for the construction of the Libbs Lake Bridge at tonight's meeting. The resolution will also ask to form a bridge aesthetics focus group to help determine the future bridge's appearance. Council meetings are held at 6 p.m. located at 14600 Minnetonka Blvd in the second-floor Council Chambers.
-
Project open house on June 17
Share Project open house on June 17 on Facebook Share Project open house on June 17 on X (formerly Twitter) Share Project open house on June 17 on Linkedin Email Project open house on June 17 linkResidents are invited to an open house to review the preliminary designs for the Libbs Lake Bridge Replacement project. Join us Wednesday, June 17, from 5-7 p.m. in the Council Chambers at Minnetonka Community Center at 14600 Minnetonka Blvd.
The City of Minnetonka is preparing design work for the Libbs Lake Bridge Replacement Project located over the channel between Libbs Lake and Gray’s Bay. See the project area map.
The bridge replacement is not scheduled until 2029; however, design work is needed in the city’s efforts to pursue grant funding for this project. This bridge was originally constructed in 1969 and is reaching the end of its service life. This project includes the replacement of the bridge, roadway and associated utilities.
Project schedule
Preliminary design has begun for the bridge replacement and design is planned through the end of 2026, at which time the City of Minnetonka will apply for state funding.
- June 17, 2026 – Public open house
- Late 2026 – Apply for state funding
- 2029 – Construction (tentative and pending project funding)
Residents are invited to an open house to review the preliminary designs for the Libbs Lake Bridge Replacement project. Join us Wednesday, June 17, from 5-7 p.m. in the Council Chambers at Minnetonka Community Center at 14600 Minnetonka Blvd.
The City of Minnetonka is preparing design work for the Libbs Lake Bridge Replacement Project located over the channel between Libbs Lake and Gray’s Bay. See the project area map.
The bridge replacement is not scheduled until 2029; however, design work is needed in the city’s efforts to pursue grant funding for this project. This bridge was originally constructed in 1969 and is reaching the end of its service life. This project includes the replacement of the bridge, roadway and associated utilities.
Project schedule
Preliminary design has begun for the bridge replacement and design is planned through the end of 2026, at which time the City of Minnetonka will apply for state funding.
- June 17, 2026 – Public open house
- Late 2026 – Apply for state funding
- 2029 – Construction (tentative and pending project funding)
-
Phone 952-939-8241 Email clong@minnetonkamn.gov -
City Engineer
Phone 952-939-8239 Email polson@minnetonkamn.gov
-
Soil borings and resident survey - April 2026
Libbs Lake Bridge has finished this stage -
Public open house - Summer 2026
Libbs Lake Bridge is currently at this stageA public open house is set for June 17 from 5-7 p.m., at Minnetonka Community Center.
-
Complete design and apply for state funding - Late 2026
this is an upcoming stage for Libbs Lake Bridge -
Construction - 2029
this is an upcoming stage for Libbs Lake Bridge