2026 Overlay project
The project includes pavement improvements, trail replacement, damaged curb and gutter replacement, utility casting replacement, and drainage improvements.
Traffic Impacts
During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.
Will I be assessed?
No. The city does not specifically assess for these improvements. These types of improvements are primarily funded through the city's street and utility funds.
Project schedule
Construction will start this summer and is expected to last approximately 4-6 weeks in each location. Detailed information regarding construction phases and schedule updates will be communicated via the project website and email/text updates. Please subscribe for updates to stay informed.
Schedules are weather-dependent and subject to change.
The project includes pavement improvements, trail replacement, damaged curb and gutter replacement, utility casting replacement, and drainage improvements.
Traffic Impacts
During construction, there will be traffic control in the area, which may include periods of lane shifts, flagging, closures and detours. Residential and business access will be maintained. Please follow construction signs, watch for traffic pattern changes and drive carefully through construction areas.
Will I be assessed?
No. The city does not specifically assess for these improvements. These types of improvements are primarily funded through the city's street and utility funds.
Project schedule
Construction will start this summer and is expected to last approximately 4-6 weeks in each location. Detailed information regarding construction phases and schedule updates will be communicated via the project website and email/text updates. Please subscribe for updates to stay informed.
Schedules are weather-dependent and subject to change.
-
Project substantially completed
Share Project substantially completed on Facebook Share Project substantially completed on X (formerly Twitter) Share Project substantially completed on Linkedin Email Project substantially completed linkThe 2026 Overlay Project is substantially completed.
- Roadway and crosswalk striping has been completed
- Final punch list items are being addressed.
This is the final update for the project. Thank you for your patience.
The 2026 Overlay Project is substantially completed.
- Roadway and crosswalk striping has been completed
- Final punch list items are being addressed.
This is the final update for the project. Thank you for your patience.
-
Striping today
Share Striping today on Facebook Share Striping today on X (formerly Twitter) Share Striping today on Linkedin Email Striping today linkWoodland Road and Minnetonka Drive
- Paving was completed this week
- Striping will begin today, marking roadways and crosswalks
Woodland Road and Minnetonka Drive
- Paving was completed this week
- Striping will begin today, marking roadways and crosswalks
-
Paving scheduled for the week of Oct. 5
Share Paving scheduled for the week of Oct. 5 on Facebook Share Paving scheduled for the week of Oct. 5 on X (formerly Twitter) Share Paving scheduled for the week of Oct. 5 on Linkedin Email Paving scheduled for the week of Oct. 5 linkWoodland Road & Minnetonka Drive:
- Milling is underway
- Paving is scheduled for the week of October 5.
Woodland Road & Minnetonka Drive:
- Milling is underway
- Paving is scheduled for the week of October 5.
-
Work along Minnetonka Drive is ongoing
Share Work along Minnetonka Drive is ongoing on Facebook Share Work along Minnetonka Drive is ongoing on X (formerly Twitter) Share Work along Minnetonka Drive is ongoing on Linkedin Email Work along Minnetonka Drive is ongoing linkWoodland Road & Minnetonka Drive
- Crews removed damaged curb and gutter. Replacement is underway.
- Concrete work and patching will continue next week.
- Milling is anticipated to begin Sept. 24.
Woodland Road & Minnetonka Drive
- Crews removed damaged curb and gutter. Replacement is underway.
- Concrete work and patching will continue next week.
- Milling is anticipated to begin Sept. 24.
-
Striping underway on Williston Road
Share Striping underway on Williston Road on Facebook Share Striping underway on Williston Road on X (formerly Twitter) Share Striping underway on Williston Road on Linkedin Email Striping underway on Williston Road link- Paving is complete on Williston Road and the Public Works parking lot
- Striping is underway today, Sept. 4 on Williston Road
- The final two segments, Minnetonka Drive and Woodland Road, are scheduled for Sept. 14.
- Paving is complete on Williston Road and the Public Works parking lot
- Striping is underway today, Sept. 4 on Williston Road
- The final two segments, Minnetonka Drive and Woodland Road, are scheduled for Sept. 14.
-
Additional patching, paving of Williston next week
Share Additional patching, paving of Williston next week on Facebook Share Additional patching, paving of Williston next week on X (formerly Twitter) Share Additional patching, paving of Williston next week on Linkedin Email Additional patching, paving of Williston next week link- After milling Williston Road, several areas were identified for additional patching which will occur Monday, Aug. 31.
- Paving on Williston is scheduled for Tuesday, Sept. 1.
- Please be aware of traffic delays next Monday and Tuesday as flaggers will be used to direct traffic.
- The Public Works parking lot was milled and is scheduled for paving Monday, Aug. 31.
- After milling Williston Road, several areas were identified for additional patching which will occur Monday, Aug. 31.
- Paving on Williston is scheduled for Tuesday, Sept. 1.
- Please be aware of traffic delays next Monday and Tuesday as flaggers will be used to direct traffic.
- The Public Works parking lot was milled and is scheduled for paving Monday, Aug. 31.
-
Crews to mill Williston this weekend
Share Crews to mill Williston this weekend on Facebook Share Crews to mill Williston this weekend on X (formerly Twitter) Share Crews to mill Williston this weekend on Linkedin Email Crews to mill Williston this weekend link- Crews completed gutter and sidewalk replacement at the Civic Center and Public Works parking lot.
- Damaged areas, including electrical and irrigation, are being repaired
- On Saturday, Aug. 22, crews will mill Williston Road.
- Paving will occur the week of Aug. 24.
- Crews completed gutter and sidewalk replacement at the Civic Center and Public Works parking lot.
- Damaged areas, including electrical and irrigation, are being repaired
- On Saturday, Aug. 22, crews will mill Williston Road.
- Paving will occur the week of Aug. 24.
-
Williston Road work underway
Share Williston Road work underway on Facebook Share Williston Road work underway on X (formerly Twitter) Share Williston Road work underway on Linkedin Email Williston Road work underway linkWilliston Road
- Crews removed damaged curb and gutter. Replacement is underway.
- Concrete work and patching will continue the week of Aug. 17.
Public Works parking lot
- Crews removed and replaced damaged curb and gutter this week.
- Areas adjacent to the replaced curb will be backfilled and patched the week of Aug. 17.
Williston Road
- Crews removed damaged curb and gutter. Replacement is underway.
- Concrete work and patching will continue the week of Aug. 17.
Public Works parking lot
- Crews removed and replaced damaged curb and gutter this week.
- Areas adjacent to the replaced curb will be backfilled and patched the week of Aug. 17.
-
Operations move to Williston Road
Share Operations move to Williston Road on Facebook Share Operations move to Williston Road on X (formerly Twitter) Share Operations move to Williston Road on Linkedin Email Operations move to Williston Road linkOakland Road progress
- Striping crews will complete work on Oakland Road today, applying roadway markings and crosswalks
Williston Road progress
- Crews will move to Williston Road on Wednesday, Aug. 12 adjacent to City Hall and Ice Arenas A and B
- Pedestrian ramps as well as concrete curb and gutter removals are underway
- Traffic will be flagged and access will be maintained, but drivers should expect delays
- Please follow flagger instructions and watch for changing traffic control
Public Works parking lot
- Improvements are coming to the Public Works parking lot
- Most work will occur after hours
Oakland Road progress
- Striping crews will complete work on Oakland Road today, applying roadway markings and crosswalks
Williston Road progress
- Crews will move to Williston Road on Wednesday, Aug. 12 adjacent to City Hall and Ice Arenas A and B
- Pedestrian ramps as well as concrete curb and gutter removals are underway
- Traffic will be flagged and access will be maintained, but drivers should expect delays
- Please follow flagger instructions and watch for changing traffic control
Public Works parking lot
- Improvements are coming to the Public Works parking lot
- Most work will occur after hours
-
Paving operations next week
Share Paving operations next week on Facebook Share Paving operations next week on X (formerly Twitter) Share Paving operations next week on Linkedin Email Paving operations next week linkThis week, crews milled the roadway and adjusted manholes. Paving operations are scheduled for Monday, Aug. 3, and are expected to be completed in a day.
Roadway striping will follow paving next week.
Watch for traffic flagging, lots of large trucks and machinery as well as changing traffic control beginning Aug. 3.
This week, crews milled the roadway and adjusted manholes. Paving operations are scheduled for Monday, Aug. 3, and are expected to be completed in a day.
Roadway striping will follow paving next week.
Watch for traffic flagging, lots of large trucks and machinery as well as changing traffic control beginning Aug. 3.
-
Phone 952-939-8237 Email csmith@minnetonkamn.gov -
Engineering Project Manager