Sherwood Force Main Replacement project

Share Sherwood Force Main Replacement project on Facebook Share Sherwood Force Main Replacement project on X (formerly Twitter) Share Sherwood Force Main Replacement project on Linkedin Email Sherwood Force Main Replacement project link
A location map. Park Ridge Drive West is highlighted between Hopkins Crossroad on the west and Live Oak Drive on the East.

Project Summary

The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.

Project schedule

Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.

Detailed information regarding construction will be communicated on this project website and via email updates.

Traffic impacts

During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.

Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.

Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.

Will I be assessed?

No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.

See project updates, including closures, below. Subscribe for updates to stay informed.

Project Summary

The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.

Project schedule

Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.

Detailed information regarding construction will be communicated on this project website and via email updates.

Traffic impacts

During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.

Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.

Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.

Will I be assessed?

No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.

See project updates, including closures, below. Subscribe for updates to stay informed.

  • Project substantially completed

    Share Project substantially completed on Facebook Share Project substantially completed on X (formerly Twitter) Share Project substantially completed on Linkedin Email Project substantially completed link

    The Contractor has completed the bulk of the work and only small clean up items remain. Thank you for your patience.

    The Contractor has completed the bulk of the work and only small clean up items remain. Thank you for your patience.

  • Curb and gutter replacement complete

    Share Curb and gutter replacement complete on Facebook Share Curb and gutter replacement complete on X (formerly Twitter) Share Curb and gutter replacement complete on Linkedin Email Curb and gutter replacement complete link

    This week’s progress included:

    • Curb and gutter complete
    • Asphalt paving complete
    • Turf Restoration began

    Next week’s activities include:

    • Turf Restoration will be completed
    • Miscellaneous punch list items

    This week’s progress included:

    • Curb and gutter complete
    • Asphalt paving complete
    • Turf Restoration began

    Next week’s activities include:

    • Turf Restoration will be completed
    • Miscellaneous punch list items
  • Restoration begins next week

    Share Restoration begins next week on Facebook Share Restoration begins next week on X (formerly Twitter) Share Restoration begins next week on Linkedin Email Restoration begins next week link

    This week’s progress included:

    • Pavement restoration prep began

    Next week’s activities include:

    • Curb and gutter installation
    • Asphalt paving
    • Restoration begins

    This week’s progress included:

    • Pavement restoration prep began

    Next week’s activities include:

    • Curb and gutter installation
    • Asphalt paving
    • Restoration begins
  • Force main lining complete; restoration begins

    Share Force main lining complete; restoration begins on Facebook Share Force main lining complete; restoration begins on X (formerly Twitter) Share Force main lining complete; restoration begins on Linkedin Email Force main lining complete; restoration begins link

    This week’s progress included:

    • Force main lining complete
    • Manhole installation complete
    • Force main connections complete and operational
    • Hydrant installation complete

    Next week’s activities include:

    • Pavement restoration and preparation begins

    This week’s progress included:

    • Force main lining complete
    • Manhole installation complete
    • Force main connections complete and operational
    • Hydrant installation complete

    Next week’s activities include:

    • Pavement restoration and preparation begins
  • Lining to continue through next week

    Share Lining to continue through next week on Facebook Share Lining to continue through next week on X (formerly Twitter) Share Lining to continue through next week on Linkedin Email Lining to continue through next week link

    This week’s progress included:

    • Force main lining continues
    • Manhole installation began

    Next week’s activities include:

    • Force main lining will be completed
    • Open cut pipe installation will begin

    This week’s progress included:

    • Force main lining continues
    • Manhole installation began

    Next week’s activities include:

    • Force main lining will be completed
    • Open cut pipe installation will begin
  • Cleaning and televising completed

    Share Cleaning and televising completed on Facebook Share Cleaning and televising completed on X (formerly Twitter) Share Cleaning and televising completed on Linkedin Email Cleaning and televising completed link

    This week’s progress included:

    • Pipe cleaning and televising completed
    • Force main lining began

    Next week’s activities include:

    • Force main lining will continue for approximately one week

    This week’s progress included:

    • Pipe cleaning and televising completed
    • Force main lining began

    Next week’s activities include:

    • Force main lining will continue for approximately one week
  • Pipe cleaning and televising underway

    Share Pipe cleaning and televising underway on Facebook Share Pipe cleaning and televising underway on X (formerly Twitter) Share Pipe cleaning and televising underway on Linkedin Email Pipe cleaning and televising underway link

    This week’s progress included:

    • Force main pipe removals complete
    • Pipe cleaning and televising have begun

    Next week’s activities include:

    • Pipe cleaning and televising will continue
    • Force main lining will begin

    This week’s progress included:

    • Force main pipe removals complete
    • Pipe cleaning and televising have begun

    Next week’s activities include:

    • Pipe cleaning and televising will continue
    • Force main lining will begin
  • Force main pipe removals begin next week

    Share Force main pipe removals begin next week on Facebook Share Force main pipe removals begin next week on X (formerly Twitter) Share Force main pipe removals begin next week on Linkedin Email Force main pipe removals begin next week link

    This week’s progress included:

    • Temporary bypass connected
    • Excavation of pits complete

    Next week’s activities include:

    • Force main pipe removals at pit locations will begin
    • Pipe cleaning will begin
    • Televising of pipe will begin

    Please be aware of traffic control changes and watch for changing traffic patterns.

    This week’s progress included:

    • Temporary bypass connected
    • Excavation of pits complete

    Next week’s activities include:

    • Force main pipe removals at pit locations will begin
    • Pipe cleaning will begin
    • Televising of pipe will begin

    Please be aware of traffic control changes and watch for changing traffic patterns.

  • Temporary bypass connections next week

    Share Temporary bypass connections next week on Facebook Share Temporary bypass connections next week on X (formerly Twitter) Share Temporary bypass connections next week on Linkedin Email Temporary bypass connections next week link

    This week’s progress included:

    • The Live Oak Drive road closure and detour were installed
    • Temporary bypass was prepared
    • Utility locating began
    • Excavation for lining pits began
    • Hydrant installation

    Next week’s activities include:

    • Connection of temporary bypass
    • Excavation for lining pits will continue

    Please be aware of traffic control changes and watch for changing traffic patterns.

    This week’s progress included:

    • The Live Oak Drive road closure and detour were installed
    • Temporary bypass was prepared
    • Utility locating began
    • Excavation for lining pits began
    • Hydrant installation

    Next week’s activities include:

    • Connection of temporary bypass
    • Excavation for lining pits will continue

    Please be aware of traffic control changes and watch for changing traffic patterns.

  • Phase two begins Aug. 17

    Share Phase two begins Aug. 17 on Facebook Share Phase two begins Aug. 17 on X (formerly Twitter) Share Phase two begins Aug. 17 on Linkedin Email Phase two begins Aug. 17 link

    Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.

    Road closure begins Aug. 17, 2026. Please follow the posted detour.

    Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.

    Activities will include:

    • Traffic control setup
    • Sewer bypass installation
    • Excavation pits for lining

    Please watch for traffic control changes and shifting traffic patterns.

    Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.

    Road closure begins Aug. 17, 2026. Please follow the posted detour.

    Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.

    Activities will include:

    • Traffic control setup
    • Sewer bypass installation
    • Excavation pits for lining

    Please watch for traffic control changes and shifting traffic patterns.

Page last updated: 22 Oct 2026, 11:27 AM