Share Phase two begins Aug. 17 on Facebook
Share Phase two begins Aug. 17 on X (formerly Twitter)
Share Phase two begins Aug. 17 on Linkedin
Email Phase two begins Aug. 17 link
Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.
Road closure begins Aug. 17, 2026. Please follow the posted detour.
Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.
Activities will include:
- Traffic control setup
- Sewer bypass installation
- Excavation pits for lining
Please watch for traffic control changes and shifting traffic patterns.
Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.
Road closure begins Aug. 17, 2026. Please follow the posted detour.
Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.
Activities will include:
- Traffic control setup
- Sewer bypass installation
- Excavation pits for lining
Please watch for traffic control changes and shifting traffic patterns.
Share Private utility operations begin next week on Facebook
Share Private utility operations begin next week on X (formerly Twitter)
Share Private utility operations begin next week on Linkedin
Email Private utility operations begin next week link
CenterPoint Energy will begin replacement of gas main beginning next week prior to the start of phase two of the Sherwood Force Main project. This private utility project is expected to last two weeks. For more information, contact CenterPoint Energy at 612-542-6198.
CenterPoint Energy will begin replacement of gas main beginning next week prior to the start of phase two of the Sherwood Force Main project. This private utility project is expected to last two weeks. For more information, contact CenterPoint Energy at 612-542-6198.
Share Timberline Road closure at Hopkins Crossroad on Facebook
Share Timberline Road closure at Hopkins Crossroad on X (formerly Twitter)
Share Timberline Road closure at Hopkins Crossroad on Linkedin
Email Timberline Road closure at Hopkins Crossroad link
Timberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.
Timberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.
Share June 6, project update on Facebook
Share June 6, project update on X (formerly Twitter)
Share June 6, project update on Linkedin
Email June 6, project update link
Live Oak Drive Closure
Live Oak Drive will open today, Friday, June 6. Thank you for your patience.
This week’s progress:
- Pipe passed all testing
- Pipe connections were made
- Roadway prepared for pavement
Next week’s activities include:
- Curb and gutter patching
- Pavement patching
Please be aware of traffic control changes and watch for changing traffic patterns.
Live Oak Drive Closure
Live Oak Drive will open today, Friday, June 6. Thank you for your patience.
This week’s progress:
- Pipe passed all testing
- Pipe connections were made
- Roadway prepared for pavement
Next week’s activities include:
- Curb and gutter patching
- Pavement patching
Please be aware of traffic control changes and watch for changing traffic patterns.
Share May 30, project update on Facebook
Share May 30, project update on X (formerly Twitter)
Share May 30, project update on Linkedin
Email May 30, project update link
Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.
This week’s progress:
- Completed utility locating
- Installed sanitary sewer pipe
Next week’s activities include:
- Pipe testing
- Complete pipe connections
- Prepare roadway for pavement patching
Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.
This week’s progress:
- Completed utility locating
- Installed sanitary sewer pipe
Next week’s activities include:
- Pipe testing
- Complete pipe connections
- Prepare roadway for pavement patching
Share May 23 Update: Live Oak Drive closure extended on Facebook
Share May 23 Update: Live Oak Drive closure extended on X (formerly Twitter)
Share May 23 Update: Live Oak Drive closure extended on Linkedin
Email May 23 Update: Live Oak Drive closure extended link
Due to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.
Please use Timberline Road to access the Sherwood Forest Neighborhood.
Next week, crews will:
- Locate existing utilities
- Install sanitary sewer pipe
- Install water main pipe
Please be aware of traffic control changes and watch for changing traffic patterns.
Due to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.
Please use Timberline Road to access the Sherwood Forest Neighborhood.
Next week, crews will:
- Locate existing utilities
- Install sanitary sewer pipe
- Install water main pipe
Please be aware of traffic control changes and watch for changing traffic patterns.
Share May 16, project update on Facebook
Share May 16, project update on X (formerly Twitter)
Share May 16, project update on Linkedin
Email May 16, project update link
Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.
This week:
- Traffic control in place
- Pavement removals began
- Construction materials arrived on site
- Sanitary sewer pipe fused
Next week's activities include
- Installing sanitary sewer pipe
- Installing water main pipe
Please watch for traffic control changes and shifting traffic patterns
Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.
This week:
- Traffic control in place
- Pavement removals began
- Construction materials arrived on site
- Sanitary sewer pipe fused
Next week's activities include
- Installing sanitary sewer pipe
- Installing water main pipe
Please watch for traffic control changes and shifting traffic patterns
Share May 9 project update on Facebook
Share May 9 project update on X (formerly Twitter)
Share May 9 project update on Linkedin
Email May 9 project update link
Work will begin on the Sherwood Force Main Replacement project beginning on May 12.
Activities will include:
- Traffic control changes
- Pavement removal
- Importing materials
- Fusing sanitary sewer pipe
- Installing sanitary sewer pipe.
Please watch for traffic control changes and shifting traffic patterns.
Work will begin on the Sherwood Force Main Replacement project beginning on May 12.
Activities will include:
- Traffic control changes
- Pavement removal
- Importing materials
- Fusing sanitary sewer pipe
- Installing sanitary sewer pipe.
Please watch for traffic control changes and shifting traffic patterns.