Sherwood Force Main Replacement project

Share Sherwood Force Main Replacement project on Facebook Share Sherwood Force Main Replacement project on X (formerly Twitter) Share Sherwood Force Main Replacement project on Linkedin Email Sherwood Force Main Replacement project link
A location map. Park Ridge Drive West is highlighted between Hopkins Crossroad on the west and Live Oak Drive on the East.

Project Summary

The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.

Project schedule

Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.

Detailed information regarding construction will be communicated on this project website and via email updates.

Traffic impacts

During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.

Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.

Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.

Will I be assessed?

No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.

See project updates, including closures, below. Subscribe for updates to stay informed.

Project Summary

The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.

Project schedule

Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.

Detailed information regarding construction will be communicated on this project website and via email updates.

Traffic impacts

During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.

Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.

Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.

Will I be assessed?

No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.

See project updates, including closures, below. Subscribe for updates to stay informed.

  • Phase two begins Aug. 17

    Share Phase two begins Aug. 17 on Facebook Share Phase two begins Aug. 17 on X (formerly Twitter) Share Phase two begins Aug. 17 on Linkedin Email Phase two begins Aug. 17 link

    Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.

    Road closure begins Aug. 17, 2026. Please follow the posted detour.

    Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.

    Activities will include:

    • Traffic control setup
    • Sewer bypass installation
    • Excavation pits for lining

    Please watch for traffic control changes and shifting traffic patterns.

    Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.

    Road closure begins Aug. 17, 2026. Please follow the posted detour.

    Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.

    Activities will include:

    • Traffic control setup
    • Sewer bypass installation
    • Excavation pits for lining

    Please watch for traffic control changes and shifting traffic patterns.

  • Private utility operations begin next week

    Share Private utility operations begin next week on Facebook Share Private utility operations begin next week on X (formerly Twitter) Share Private utility operations begin next week on Linkedin Email Private utility operations begin next week link

    CenterPoint Energy will begin replacement of gas main beginning next week prior to the start of phase two of the Sherwood Force Main project. This private utility project is expected to last two weeks. For more information, contact CenterPoint Energy at 612-542-6198.

    CenterPoint Energy will begin replacement of gas main beginning next week prior to the start of phase two of the Sherwood Force Main project. This private utility project is expected to last two weeks. For more information, contact CenterPoint Energy at 612-542-6198.

  • Timberline Road closure at Hopkins Crossroad

    Share Timberline Road closure at Hopkins Crossroad on Facebook Share Timberline Road closure at Hopkins Crossroad on X (formerly Twitter) Share Timberline Road closure at Hopkins Crossroad on Linkedin Email Timberline Road closure at Hopkins Crossroad link

    Timberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.

    Timberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.

  • June 6, project update

    Share June 6, project update on Facebook Share June 6, project update on X (formerly Twitter) Share June 6, project update on Linkedin Email June 6, project update link

    Live Oak Drive Closure

    Live Oak Drive will open today, Friday, June 6. Thank you for your patience.

    This week’s progress:

    • Pipe passed all testing
    • Pipe connections were made
    • Roadway prepared for pavement


    Next week’s activities include:

    • Curb and gutter patching
    • Pavement patching


    Please be aware of traffic control changes and watch for changing traffic patterns.

    Live Oak Drive Closure

    Live Oak Drive will open today, Friday, June 6. Thank you for your patience.

    This week’s progress:

    • Pipe passed all testing
    • Pipe connections were made
    • Roadway prepared for pavement


    Next week’s activities include:

    • Curb and gutter patching
    • Pavement patching


    Please be aware of traffic control changes and watch for changing traffic patterns.

  • May 30, project update

    Share May 30, project update on Facebook Share May 30, project update on X (formerly Twitter) Share May 30, project update on Linkedin Email May 30, project update link

    Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.

    This week’s progress:

    • Completed utility locating
    • Installed sanitary sewer pipe

    Next week’s activities include:

    • Pipe testing
    • Complete pipe connections
    • Prepare roadway for pavement patching

    Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.

    This week’s progress:

    • Completed utility locating
    • Installed sanitary sewer pipe

    Next week’s activities include:

    • Pipe testing
    • Complete pipe connections
    • Prepare roadway for pavement patching
  • May 23 Update: Live Oak Drive closure extended

    Share May 23 Update: Live Oak Drive closure extended on Facebook Share May 23 Update: Live Oak Drive closure extended on X (formerly Twitter) Share May 23 Update: Live Oak Drive closure extended on Linkedin Email May 23 Update: Live Oak Drive closure extended link

    Due to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.

    Please use Timberline Road to access the Sherwood Forest Neighborhood.

    Next week, crews will:

    • Locate existing utilities
    • Install sanitary sewer pipe
    • Install water main pipe

    Please be aware of traffic control changes and watch for changing traffic patterns.

    Due to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.

    Please use Timberline Road to access the Sherwood Forest Neighborhood.

    Next week, crews will:

    • Locate existing utilities
    • Install sanitary sewer pipe
    • Install water main pipe

    Please be aware of traffic control changes and watch for changing traffic patterns.

  • May 16, project update

    Share May 16, project update on Facebook Share May 16, project update on X (formerly Twitter) Share May 16, project update on Linkedin Email May 16, project update link

    Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.

    This week:

    • Traffic control in place
    • Pavement removals began
    • Construction materials arrived on site
    • Sanitary sewer pipe fused

    Next week's activities include

    • Installing sanitary sewer pipe
    • Installing water main pipe

    Please watch for traffic control changes and shifting traffic patterns

    Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.

    This week:

    • Traffic control in place
    • Pavement removals began
    • Construction materials arrived on site
    • Sanitary sewer pipe fused

    Next week's activities include

    • Installing sanitary sewer pipe
    • Installing water main pipe

    Please watch for traffic control changes and shifting traffic patterns

  • May 9 project update

    Share May 9 project update on Facebook Share May 9 project update on X (formerly Twitter) Share May 9 project update on Linkedin Email May 9 project update link

    Work will begin on the Sherwood Force Main Replacement project beginning on May 12.

    Activities will include:

    • Traffic control changes
    • Pavement removal
    • Importing materials
    • Fusing sanitary sewer pipe
    • Installing sanitary sewer pipe.

    Please watch for traffic control changes and shifting traffic patterns.

    Work will begin on the Sherwood Force Main Replacement project beginning on May 12.

    Activities will include:

    • Traffic control changes
    • Pavement removal
    • Importing materials
    • Fusing sanitary sewer pipe
    • Installing sanitary sewer pipe.

    Please watch for traffic control changes and shifting traffic patterns.

Page last updated: 10 Aug 2026, 12:59 PM