Sherwood Force Main Replacement project

Share Sherwood Force Main Replacement project on Facebook Share Sherwood Force Main Replacement project on X (formerly Twitter) Share Sherwood Force Main Replacement project on Linkedin Email Sherwood Force Main Replacement project link
A location map. Park Ridge Drive West is highlighted between Hopkins Crossroad on the west and Live Oak Drive on the East.

Project Summary

The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.

Project schedule

Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.

Detailed information regarding construction will be communicated on this project website and via email updates.

Traffic impacts

During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.

Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.

Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.

Will I be assessed?

No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.

See project updates, including closures, below. Subscribe for updates to stay informed.

Project Summary

The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.

Project schedule

Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.

Detailed information regarding construction will be communicated on this project website and via email updates.

Traffic impacts

During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.

Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.

Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.

Will I be assessed?

No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.

See project updates, including closures, below. Subscribe for updates to stay informed.

  • May 16, project update

    Share May 16, project update on Facebook Share May 16, project update on X (formerly Twitter) Share May 16, project update on Linkedin Email May 16, project update link

    Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.

    This week:

    • Traffic control in place
    • Pavement removals began
    • Construction materials arrived on site
    • Sanitary sewer pipe fused

    Next week's activities include

    • Installing sanitary sewer pipe
    • Installing water main pipe

    Please watch for traffic control changes and shifting traffic patterns

    Live Oak Drive will be closed at Hopkins Crossroad from May 19 -30. The closure will allow for the installation of new sanitary sewer and water main pipe. Use the posted detour.

    This week:

    • Traffic control in place
    • Pavement removals began
    • Construction materials arrived on site
    • Sanitary sewer pipe fused

    Next week's activities include

    • Installing sanitary sewer pipe
    • Installing water main pipe

    Please watch for traffic control changes and shifting traffic patterns

  • May 9 project update

    Share May 9 project update on Facebook Share May 9 project update on X (formerly Twitter) Share May 9 project update on Linkedin Email May 9 project update link

    Work will begin on the Sherwood Force Main Replacement project beginning on May 12.

    Activities will include:

    • Traffic control changes
    • Pavement removal
    • Importing materials
    • Fusing sanitary sewer pipe
    • Installing sanitary sewer pipe.

    Please watch for traffic control changes and shifting traffic patterns.

    Work will begin on the Sherwood Force Main Replacement project beginning on May 12.

    Activities will include:

    • Traffic control changes
    • Pavement removal
    • Importing materials
    • Fusing sanitary sewer pipe
    • Installing sanitary sewer pipe.

    Please watch for traffic control changes and shifting traffic patterns.

Page last updated: 18 Sep 2026, 01:08 PM