Sherwood Force Main Replacement project
Project Summary
The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.
Project schedule
Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.
Detailed information regarding construction will be communicated on this project website and via email updates.
Traffic impacts
During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.
Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.
Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.
Will I be assessed?
No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.
See project updates, including closures, below. Subscribe for updates to stay informed.
Project Summary
The City of Minnetonka will complete sanitary sew improvements along Park Ridge Drive West and Live Oak Drive, west of Hopkins Crossroad. This project replaces a 53-year-old sewer force main from Sherwood Lift Station to the new force main that was installed at Live Oak Drive and Hopkins Crossroad in 2025.
Project schedule
Construction is scheduled to begin on or around Monday, Aug. 17 and will last approximately 8-10 weeks.
Detailed information regarding construction will be communicated on this project website and via email updates.
Traffic impacts
During construction, Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and materials.
Park Ridge Drive West and Live Oak Drive east of the closure will remain open to traffic. Access to driveways will be available, with the exception of short closures for pipe connections.
Follow construction signs and watch for traffic pattern changes. Drive carefully and expect delays.
Will I be assessed?
No. The City of Minnetonka does not assess for these improvements. The project is funded through the city's Utility Fund.
See project updates, including closures, below. Subscribe for updates to stay informed.
-
Cleaning and televising completed
Share Cleaning and televising completed on Facebook Share Cleaning and televising completed on X (formerly Twitter) Share Cleaning and televising completed on Linkedin Email Cleaning and televising completed linkThis week’s progress included:
- Pipe cleaning and televising completed
- Force main lining began
Next week’s activities include:
- Force main lining will continue for approximately one week
This week’s progress included:
- Pipe cleaning and televising completed
- Force main lining began
Next week’s activities include:
- Force main lining will continue for approximately one week
-
Pipe cleaning and televising underway
Share Pipe cleaning and televising underway on Facebook Share Pipe cleaning and televising underway on X (formerly Twitter) Share Pipe cleaning and televising underway on Linkedin Email Pipe cleaning and televising underway linkThis week’s progress included:
- Force main pipe removals complete
- Pipe cleaning and televising have begun
Next week’s activities include:
- Pipe cleaning and televising will continue
- Force main lining will begin
This week’s progress included:
- Force main pipe removals complete
- Pipe cleaning and televising have begun
Next week’s activities include:
- Pipe cleaning and televising will continue
- Force main lining will begin
-
Force main pipe removals begin next week
Share Force main pipe removals begin next week on Facebook Share Force main pipe removals begin next week on X (formerly Twitter) Share Force main pipe removals begin next week on Linkedin Email Force main pipe removals begin next week linkThis week’s progress included:
- Temporary bypass connected
- Excavation of pits complete
Next week’s activities include:
- Force main pipe removals at pit locations will begin
- Pipe cleaning will begin
- Televising of pipe will begin
Please be aware of traffic control changes and watch for changing traffic patterns.
This week’s progress included:
- Temporary bypass connected
- Excavation of pits complete
Next week’s activities include:
- Force main pipe removals at pit locations will begin
- Pipe cleaning will begin
- Televising of pipe will begin
Please be aware of traffic control changes and watch for changing traffic patterns.
-
Temporary bypass connections next week
Share Temporary bypass connections next week on Facebook Share Temporary bypass connections next week on X (formerly Twitter) Share Temporary bypass connections next week on Linkedin Email Temporary bypass connections next week linkThis week’s progress included:
- The Live Oak Drive road closure and detour were installed
- Temporary bypass was prepared
- Utility locating began
- Excavation for lining pits began
- Hydrant installation
Next week’s activities include:
- Connection of temporary bypass
- Excavation for lining pits will continue
Please be aware of traffic control changes and watch for changing traffic patterns.
This week’s progress included:
- The Live Oak Drive road closure and detour were installed
- Temporary bypass was prepared
- Utility locating began
- Excavation for lining pits began
- Hydrant installation
Next week’s activities include:
- Connection of temporary bypass
- Excavation for lining pits will continue
Please be aware of traffic control changes and watch for changing traffic patterns.
-
Phase two begins Aug. 17
Share Phase two begins Aug. 17 on Facebook Share Phase two begins Aug. 17 on X (formerly Twitter) Share Phase two begins Aug. 17 on Linkedin Email Phase two begins Aug. 17 linkWork will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.
Road closure begins Aug. 17, 2026. Please follow the posted detour.
Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.
Activities will include:
- Traffic control setup
- Sewer bypass installation
- Excavation pits for lining
Please watch for traffic control changes and shifting traffic patterns.
Work will begin on phase two of the Sherwood Force Main Replacement project on Aug.17, 2026.
Road closure begins Aug. 17, 2026. Please follow the posted detour.
Live Oak Drive will be closed between Lakeview Lane West and Park Ridge Drive West to stage contractor equipment and operations. This closure will last the duration of the project.
Activities will include:
- Traffic control setup
- Sewer bypass installation
- Excavation pits for lining
Please watch for traffic control changes and shifting traffic patterns.
-
Private utility operations begin next week
Share Private utility operations begin next week on Facebook Share Private utility operations begin next week on X (formerly Twitter) Share Private utility operations begin next week on Linkedin Email Private utility operations begin next week linkCenterPoint Energy will begin replacement of gas main beginning next week prior to the start of phase two of the Sherwood Force Main project. This private utility project is expected to last two weeks. For more information, contact CenterPoint Energy at 612-542-6198.
CenterPoint Energy will begin replacement of gas main beginning next week prior to the start of phase two of the Sherwood Force Main project. This private utility project is expected to last two weeks. For more information, contact CenterPoint Energy at 612-542-6198.
-
Timberline Road closure at Hopkins Crossroad
Share Timberline Road closure at Hopkins Crossroad on Facebook Share Timberline Road closure at Hopkins Crossroad on X (formerly Twitter) Share Timberline Road closure at Hopkins Crossroad on Linkedin Email Timberline Road closure at Hopkins Crossroad linkTimberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.
Timberline Road will be closed at Hopkins Crossroad on Tuesday, July 22 for one day as crews perform maintenance on a manhole in the area. Thank you for your patience while this work is completed.
-
June 6, project update
Share June 6, project update on Facebook Share June 6, project update on X (formerly Twitter) Share June 6, project update on Linkedin Email June 6, project update linkLive Oak Drive Closure
Live Oak Drive will open today, Friday, June 6. Thank you for your patience.
This week’s progress:
- Pipe passed all testing
- Pipe connections were made
- Roadway prepared for pavement
Next week’s activities include:
- Curb and gutter patching
- Pavement patching
Please be aware of traffic control changes and watch for changing traffic patterns.
Live Oak Drive Closure
Live Oak Drive will open today, Friday, June 6. Thank you for your patience.
This week’s progress:
- Pipe passed all testing
- Pipe connections were made
- Roadway prepared for pavement
Next week’s activities include:
- Curb and gutter patching
- Pavement patching
Please be aware of traffic control changes and watch for changing traffic patterns.
-
May 30, project update
Share May 30, project update on Facebook Share May 30, project update on X (formerly Twitter) Share May 30, project update on Linkedin Email May 30, project update linkLive Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.
This week’s progress:
- Completed utility locating
- Installed sanitary sewer pipe
Next week’s activities include:
- Pipe testing
- Complete pipe connections
- Prepare roadway for pavement patching
Live Oak Drive closure: Live Oak Drive is scheduled to reopen on June 6. Thank you for your patience.
This week’s progress:
- Completed utility locating
- Installed sanitary sewer pipe
Next week’s activities include:
- Pipe testing
- Complete pipe connections
- Prepare roadway for pavement patching
-
May 23 Update: Live Oak Drive closure extended
Share May 23 Update: Live Oak Drive closure extended on Facebook Share May 23 Update: Live Oak Drive closure extended on X (formerly Twitter) Share May 23 Update: Live Oak Drive closure extended on Linkedin Email May 23 Update: Live Oak Drive closure extended linkDue to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.
Please use Timberline Road to access the Sherwood Forest Neighborhood.
Next week, crews will:
- Locate existing utilities
- Install sanitary sewer pipe
- Install water main pipe
Please be aware of traffic control changes and watch for changing traffic patterns.
Due to wet weather and difficulty locating existing utilities, the Live Oak Drive closure will be extended one additional week to Friday, June 6. We apologize for the continued inconvenience and thank you for your patience.
Please use Timberline Road to access the Sherwood Forest Neighborhood.
Next week, crews will:
- Locate existing utilities
- Install sanitary sewer pipe
- Install water main pipe
Please be aware of traffic control changes and watch for changing traffic patterns.
-
Phone 952-939-8230 Email ajsoland@minnetonkamn.gov -
Phone 952-988-8410 Email mkuno@minnetonkamn.gov