2025 Mill and Overlay Project (Residential Areas)

Share 2025 Mill and Overlay Project (Residential Areas) on Facebook Share 2025 Mill and Overlay Project (Residential Areas) on Twitter Share 2025 Mill and Overlay Project (Residential Areas) on Linkedin Email 2025 Mill and Overlay Project (Residential Areas) link

Overlay projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase one

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase two

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase three

  • A new layer of asphalt is applied to the roadway.

Overlay projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase one

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase two

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase three

  • A new layer of asphalt is applied to the roadway.
  • 2025 Mill and Overlay project complete

    Share 2025 Mill and Overlay project complete on Facebook Share 2025 Mill and Overlay project complete on Twitter Share 2025 Mill and Overlay project complete on Linkedin Email 2025 Mill and Overlay project complete link

    With cooler temperatures moving in, the 2025 Mill and Overlay project is now complete. Several streets were not completed this summer due to continued wet conditions. Those streets include:

    • Gizmo Lane
    • F Street
    • E Street
    • Chippewa Road
    • Birch Place
    • Atwater Street
    • W 34th Circle
    • W 34th Street
    • Delta Ave

    Those streets will be completed in 2026.

  • Oct. 20 project update

    Share Oct. 20 project update on Facebook Share Oct. 20 project update on Twitter Share Oct. 20 project update on Linkedin Email Oct. 20 project update link

    Due to weather conditions, phase 3 will begin on Ann Lane and Sandra Lane on Oct. 22.

    Please have all vehicles moved off the street for these operations.

  • Oct. 15 project update

    Share Oct. 15 project update on Facebook Share Oct. 15 project update on Twitter Share Oct. 15 project update on Linkedin Email Oct. 15 project update link

    Ann Lane and Sandra Lane will begin Phase 3 on Monday, Oct. 20, pending favorable weather. Please have all vehicles moved off the street.

  • Oct. 8 project update

    Share Oct. 8 project update on Facebook Share Oct. 8 project update on Twitter Share Oct. 8 project update on Linkedin Email Oct. 8 project update link

    Phase 1 will start the week of Oct. 13 for Ann Lane and Sandra Lane.

  • Oct. 2 project update

    Share Oct. 2 project update on Facebook Share Oct. 2 project update on Twitter Share Oct. 2 project update on Linkedin Email Oct. 2 project update link

    Area 3 complete. Parking restrictions are lifted.

    Area 4, phase 1 to begin the week of Oct. 6.

  • Sept. 24 project update

    Share Sept. 24 project update on Facebook Share Sept. 24 project update on Twitter Share Sept. 24 project update on Linkedin Email Sept. 24 project update link

    Phase 1 and 2 in progress for McKenzie Blvd

    Phase 3 week of Sept 22nd : Skyview Dr, Highland Road, Belvior Dr, and Thomas Ave.

    Phase 3 week of Sept 29th: Redding Ridge Dr, Red Oak Rdg, and McKenzie Blvd.

  • Sept. 15 project update

    Share Sept. 15 project update on Facebook Share Sept. 15 project update on Twitter Share Sept. 15 project update on Linkedin Email Sept. 15 project update link

    Updates listed for area 3.

    Phase 1

    Main milling is completed. Detail milling in progress.


    Phase 2

    In progress.


    Phase 3

    Paving Day Place and Victoria Drive on Sept. 16.

    Wendover Court Ct and Skyview Road (North) Sept. 17 pending weather.

  • Sept. 1 project update

    Share Sept. 1 project update on Facebook Share Sept. 1 project update on Twitter Share Sept. 1 project update on Linkedin Email Sept. 1 project update link

    Area 2 is complete.

    Area 3 begins this week.

  • Aug. 12 project update

    Share Aug. 12 project update on Facebook Share Aug. 12 project update on Twitter Share Aug. 12 project update on Linkedin Email Aug. 12 project update link

    Phase 3 will begin for Royal Oaks Drive on Aug. 13, pending weather conditions.

    Phase 3 will begin for Winterset Drive on Aug. 14. Starting the week of Aug.18, Phase 3 will begin for Barbara Drive, Joanne Lane, Nelson Drive, Diane Drive and Church Lane. These projects will be weather dependent.

    Phase 3 will begin for Pioneer Road starting the week of Aug. 25.

  • July 31 project update

    Share July 31 project update on Facebook Share July 31 project update on Twitter Share July 31 project update on Linkedin Email July 31 project update link

    Phase 3 complete for Birchwood Lane, Carleton Road and Arlington Drive.

    Phase 3 will begin on Royal Oaks Drive, Merilee Rive and Valley Road the week of Aug. 3, weather permitting.

Page last updated: 27 Oct 2025, 08:47 AM