2026 Mill and Pave project

Share 2026 Mill and Pave project on Facebook Share 2026 Mill and Pave project on X (formerly Twitter) Share 2026 Mill and Pave project on Linkedin Email 2026 Mill and Pave project link

The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.

Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase I

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase II

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase III

  • A new layer of asphalt is applied to the roadway.

The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.

Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase I

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase II

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase III

  • A new layer of asphalt is applied to the roadway.
  • Bantas Point Lane Paving today

    Share Bantas Point Lane Paving today on Facebook Share Bantas Point Lane Paving today on X (formerly Twitter) Share Bantas Point Lane Paving today on Linkedin Email Bantas Point Lane Paving today link

    Phase III is complete for Crosby Bove and Crosby Road

    Paving (phase III) begins today for Bantas Point Lane and Pine Street. Please keep all vehicles off the street. Park on Bantas Point Road if needed.

    Teams will return on Tuesday, July 21 to complete Bantas Point Road.

    There will be a tack oil sprayed on the road surface before asphalt is applied. Drive with caution. Wet tack oil will transfer to driveways. When the road is paved, it is okay to drive on. Please allow 3 - 7 days for the asphalt to start the curing process.

    Thank you for your cooperation and patience as this project progresses.

    Phase III is complete for Crosby Bove and Crosby Road

    Paving (phase III) begins today for Bantas Point Lane and Pine Street. Please keep all vehicles off the street. Park on Bantas Point Road if needed.

    Teams will return on Tuesday, July 21 to complete Bantas Point Road.

    There will be a tack oil sprayed on the road surface before asphalt is applied. Drive with caution. Wet tack oil will transfer to driveways. When the road is paved, it is okay to drive on. Please allow 3 - 7 days for the asphalt to start the curing process.

    Thank you for your cooperation and patience as this project progresses.

  • Phase III begins on Bantas Point Lane Thursday

    Share Phase III begins on Bantas Point Lane Thursday on Facebook Share Phase III begins on Bantas Point Lane Thursday on X (formerly Twitter) Share Phase III begins on Bantas Point Lane Thursday on Linkedin Email Phase III begins on Bantas Point Lane Thursday link

    Phase III is complete for Crosby Cove, but will continue tomorrow on Crosby Road. Paving operations will begin Thursday, July 16 on Bantas Point Lane Thursday.

    Please have all vehicles off the road.

    Phase III is complete for Crosby Cove, but will continue tomorrow on Crosby Road. Paving operations will begin Thursday, July 16 on Bantas Point Lane Thursday.

    Please have all vehicles off the road.

  • Area 2 Phase II completed; paving tomorrow

    Share Area 2 Phase II completed; paving tomorrow on Facebook Share Area 2 Phase II completed; paving tomorrow on X (formerly Twitter) Share Area 2 Phase II completed; paving tomorrow on Linkedin Email Area 2 Phase II completed; paving tomorrow link

    Phase II is complete in Area 2. Phase III will begin for Crosby Road and Crosby Cove tomorrow.

    No parking on the street tomorrow.

    Phase II is complete in Area 2. Phase III will begin for Crosby Road and Crosby Cove tomorrow.

    No parking on the street tomorrow.

  • Area one complete; Area two begins June 30

    Share Area one complete; Area two begins June 30 on Facebook Share Area one complete; Area two begins June 30 on X (formerly Twitter) Share Area one complete; Area two begins June 30 on Linkedin Email Area one complete; Area two begins June 30 link

    UPDATE: A previous version of this story noted that repairs in Area two were expected to begin on July 1.

    Area one has been completed.

    Work on Area two begins Tuesday, June 30. Phase 1 is set to begin, weather permitting. This area includes:

    • Bantas Point Road
    • Bantas Point Lane
    • Crosby Road (South of McGinty)
    • Crosby Grove

    See the area map for further details.

    On-street parking is prohibited Monday through Friday between 6 a.m. and 6 p.m. Weekend parking is not restricted.

    UPDATE: A previous version of this story noted that repairs in Area two were expected to begin on July 1.

    Area one has been completed.

    Work on Area two begins Tuesday, June 30. Phase 1 is set to begin, weather permitting. This area includes:

    • Bantas Point Road
    • Bantas Point Lane
    • Crosby Road (South of McGinty)
    • Crosby Grove

    See the area map for further details.

    On-street parking is prohibited Monday through Friday between 6 a.m. and 6 p.m. Weekend parking is not restricted.

  • Area one moves to phase 3

    Share Area one moves to phase 3 on Facebook Share Area one moves to phase 3 on X (formerly Twitter) Share Area one moves to phase 3 on Linkedin Email Area one moves to phase 3 link

    Phase 3 complete for Gizmo Lane, F Street, E Street, Chippewa Road North and Birch Place North. Phase 3 will continue the week of June 22.

    Area two, phase one set to begin the week of June 29. This area is on the northwest side of the city and includes:

    • Crosby Road
    • Crosby Cove
    • Bantas Point Road
    • Bantas Point Lane

    See the project map for further details of the project area.

    Phase 3 complete for Gizmo Lane, F Street, E Street, Chippewa Road North and Birch Place North. Phase 3 will continue the week of June 22.

    Area two, phase one set to begin the week of June 29. This area is on the northwest side of the city and includes:

    • Crosby Road
    • Crosby Cove
    • Bantas Point Road
    • Bantas Point Lane

    See the project map for further details of the project area.

  • Area 1 moves to Phase two

    Share Area 1 moves to Phase two on Facebook Share Area 1 moves to Phase two on X (formerly Twitter) Share Area 1 moves to Phase two on Linkedin Email Area 1 moves to Phase two link

    Phase one is complete in area one. Phase two is ongoing this week. Phase three will begin the week of June 15.

    Phase one is complete in area one. Phase two is ongoing this week. Phase three will begin the week of June 15.

  • Project begins in Area 1 June 2

    Share Project begins in Area 1 June 2 on Facebook Share Project begins in Area 1 June 2 on X (formerly Twitter) Share Project begins in Area 1 June 2 on Linkedin Email Project begins in Area 1 June 2 link

    Progress on the 2026 Mill and Pave project is set to begin on June 2 in Area 1. This area includes (from east to west):

    • Gizmo Lane
    • F Street
    • E Street
    • Delta Avenue
    • Chippewa Road
    • Birch Place
    • W 34th Circle
    • 34th St West.

    Progress on the 2026 Mill and Pave project is set to begin on June 2 in Area 1. This area includes (from east to west):

    • Gizmo Lane
    • F Street
    • E Street
    • Delta Avenue
    • Chippewa Road
    • Birch Place
    • W 34th Circle
    • 34th St West.
  • 2026 Mill and Pave map posted

    Share 2026 Mill and Pave map posted on Facebook Share 2026 Mill and Pave map posted on X (formerly Twitter) Share 2026 Mill and Pave map posted on Linkedin Email 2026 Mill and Pave map posted link

    The 2026 Mill and Pave map has been posted. The map indicates areas that will be constructed during the summer of 2026.

    The 2026 Mill and Pave map has been posted. The map indicates areas that will be constructed during the summer of 2026.

  • 2025 Mill and Overlay project complete

    Share 2025 Mill and Overlay project complete on Facebook Share 2025 Mill and Overlay project complete on X (formerly Twitter) Share 2025 Mill and Overlay project complete on Linkedin Email 2025 Mill and Overlay project complete link

    With cooler temperatures moving in, the 2025 Mill and Overlay project is now complete. Several streets were not completed this summer due to continued wet conditions. Those streets include:

    • Gizmo Lane
    • F Street
    • E Street
    • Chippewa Road
    • Birch Place
    • Atwater Street
    • W 34th Circle
    • W 34th Street
    • Delta Ave

    Those streets will be completed in 2026.

    With cooler temperatures moving in, the 2025 Mill and Overlay project is now complete. Several streets were not completed this summer due to continued wet conditions. Those streets include:

    • Gizmo Lane
    • F Street
    • E Street
    • Chippewa Road
    • Birch Place
    • Atwater Street
    • W 34th Circle
    • W 34th Street
    • Delta Ave

    Those streets will be completed in 2026.

  • Oct. 20 project update

    Share Oct. 20 project update on Facebook Share Oct. 20 project update on X (formerly Twitter) Share Oct. 20 project update on Linkedin Email Oct. 20 project update link

    Due to weather conditions, phase 3 will begin on Ann Lane and Sandra Lane on Oct. 22.

    Please have all vehicles moved off the street for these operations.

    Due to weather conditions, phase 3 will begin on Ann Lane and Sandra Lane on Oct. 22.

    Please have all vehicles moved off the street for these operations.