2026 Mill and Pave project

Share 2026 Mill and Pave project on Facebook Share 2026 Mill and Pave project on X (formerly Twitter) Share 2026 Mill and Pave project on Linkedin Email 2026 Mill and Pave project link

The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.

Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase I

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase II

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase III

  • A new layer of asphalt is applied to the roadway.

The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.

Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.

Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.

Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.

Street overlay projects proceed as follows:

Pre-phase

  • Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion

Phase I

  • The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase

Phase II

  • Manholes and gate valves are raised to accommodate new the new layers of asphalt.

Phase III

  • A new layer of asphalt is applied to the roadway.
  • Oct. 15 project update

    Share Oct. 15 project update on Facebook Share Oct. 15 project update on X (formerly Twitter) Share Oct. 15 project update on Linkedin Email Oct. 15 project update link

    Ann Lane and Sandra Lane will begin Phase 3 on Monday, Oct. 20, pending favorable weather. Please have all vehicles moved off the street.

    Ann Lane and Sandra Lane will begin Phase 3 on Monday, Oct. 20, pending favorable weather. Please have all vehicles moved off the street.

  • Oct. 8 project update

    Share Oct. 8 project update on Facebook Share Oct. 8 project update on X (formerly Twitter) Share Oct. 8 project update on Linkedin Email Oct. 8 project update link

    Phase 1 will start the week of Oct. 13 for Ann Lane and Sandra Lane.

    Phase 1 will start the week of Oct. 13 for Ann Lane and Sandra Lane.

  • Oct. 2 project update

    Share Oct. 2 project update on Facebook Share Oct. 2 project update on X (formerly Twitter) Share Oct. 2 project update on Linkedin Email Oct. 2 project update link

    Area 3 complete. Parking restrictions are lifted.

    Area 4, phase 1 to begin the week of Oct. 6.

    Area 3 complete. Parking restrictions are lifted.

    Area 4, phase 1 to begin the week of Oct. 6.

  • Sept. 24 project update

    Share Sept. 24 project update on Facebook Share Sept. 24 project update on X (formerly Twitter) Share Sept. 24 project update on Linkedin Email Sept. 24 project update link

    Phase 1 and 2 in progress for McKenzie Blvd

    Phase 3 week of Sept 22nd : Skyview Dr, Highland Road, Belvior Dr, and Thomas Ave.

    Phase 3 week of Sept 29th: Redding Ridge Dr, Red Oak Rdg, and McKenzie Blvd.

    Phase 1 and 2 in progress for McKenzie Blvd

    Phase 3 week of Sept 22nd : Skyview Dr, Highland Road, Belvior Dr, and Thomas Ave.

    Phase 3 week of Sept 29th: Redding Ridge Dr, Red Oak Rdg, and McKenzie Blvd.

  • Sept. 15 project update

    Share Sept. 15 project update on Facebook Share Sept. 15 project update on X (formerly Twitter) Share Sept. 15 project update on Linkedin Email Sept. 15 project update link

    Updates listed for area 3.

    Phase 1

    Main milling is completed. Detail milling in progress.


    Phase 2

    In progress.


    Phase 3

    Paving Day Place and Victoria Drive on Sept. 16.

    Wendover Court Ct and Skyview Road (North) Sept. 17 pending weather.

    Updates listed for area 3.

    Phase 1

    Main milling is completed. Detail milling in progress.


    Phase 2

    In progress.


    Phase 3

    Paving Day Place and Victoria Drive on Sept. 16.

    Wendover Court Ct and Skyview Road (North) Sept. 17 pending weather.

  • Sept. 1 project update

    Share Sept. 1 project update on Facebook Share Sept. 1 project update on X (formerly Twitter) Share Sept. 1 project update on Linkedin Email Sept. 1 project update link

    Area 2 is complete.

    Area 3 begins this week.

    Area 2 is complete.

    Area 3 begins this week.

  • Aug. 12 project update

    Share Aug. 12 project update on Facebook Share Aug. 12 project update on X (formerly Twitter) Share Aug. 12 project update on Linkedin Email Aug. 12 project update link

    Phase 3 will begin for Royal Oaks Drive on Aug. 13, pending weather conditions.

    Phase 3 will begin for Winterset Drive on Aug. 14. Starting the week of Aug.18, Phase 3 will begin for Barbara Drive, Joanne Lane, Nelson Drive, Diane Drive and Church Lane. These projects will be weather dependent.

    Phase 3 will begin for Pioneer Road starting the week of Aug. 25.

    Phase 3 will begin for Royal Oaks Drive on Aug. 13, pending weather conditions.

    Phase 3 will begin for Winterset Drive on Aug. 14. Starting the week of Aug.18, Phase 3 will begin for Barbara Drive, Joanne Lane, Nelson Drive, Diane Drive and Church Lane. These projects will be weather dependent.

    Phase 3 will begin for Pioneer Road starting the week of Aug. 25.

  • July 31 project update

    Share July 31 project update on Facebook Share July 31 project update on X (formerly Twitter) Share July 31 project update on Linkedin Email July 31 project update link

    Phase 3 complete for Birchwood Lane, Carleton Road and Arlington Drive.

    Phase 3 will begin on Royal Oaks Drive, Merilee Rive and Valley Road the week of Aug. 3, weather permitting.

    Phase 3 complete for Birchwood Lane, Carleton Road and Arlington Drive.

    Phase 3 will begin on Royal Oaks Drive, Merilee Rive and Valley Road the week of Aug. 3, weather permitting.

  • July 23 project update

    Share July 23 project update on Facebook Share July 23 project update on X (formerly Twitter) Share July 23 project update on Linkedin Email July 23 project update link

    Phase 2 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 3 delayed due to weather.

    Phase 2 complete for Royal Oaks Drive, Merilee Drive, and Valley Road. Phase 3 delayed due to weather.

    Phase 1 is in progress for Winterset Drive, Barbara Drive, Joanne Lane, Diane Drive, Nelson Drive, Church Lane, and Pioneer Road.

    Phase 2 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 3 delayed due to weather.

    Phase 2 complete for Royal Oaks Drive, Merilee Drive, and Valley Road. Phase 3 delayed due to weather.

    Phase 1 is in progress for Winterset Drive, Barbara Drive, Joanne Lane, Diane Drive, Nelson Drive, Church Lane, and Pioneer Road.

  • July 11, project updates

    Share July 11, project updates on Facebook Share July 11, project updates on X (formerly Twitter) Share July 11, project updates on Linkedin Email July 11, project updates link

    Phase 3 complete for Maywood Lane and Jane Lane.

    Phase 1 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 2 in progress.

    Phase 1 will begin today on Valley Road heading East into Winterset Drive to the Barbara Drive neighborhood. Parking restriction will resume.

    Phase 3 complete for Maywood Lane and Jane Lane.

    Phase 1 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 2 in progress.

    Phase 1 will begin today on Valley Road heading East into Winterset Drive to the Barbara Drive neighborhood. Parking restriction will resume.

Page last updated: 15 Sep 2026, 01:40 PM