Share 2026 Mill and Pave project on FacebookShare 2026 Mill and Pave project on X (formerly Twitter)Share 2026 Mill and Pave project on LinkedinEmail 2026 Mill and Pave project link
The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.
Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.
Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.
Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.
Street overlay projects proceed as follows:
Pre-phase
Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion
Phase I
The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase
Phase II
Manholes and gate valves are raised to accommodate new the new layers of asphalt.
Phase III
A new layer of asphalt is applied to the roadway.
The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.
Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.
Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.
Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.
Street overlay projects proceed as follows:
Pre-phase
Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion
Phase I
The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase
Phase II
Manholes and gate valves are raised to accommodate new the new layers of asphalt.
Share Aug. 12 project update on FacebookShare Aug. 12 project update on X (formerly Twitter)Share Aug. 12 project update on LinkedinEmail Aug. 12 project update link
Phase 3 will begin for Royal Oaks Drive on Aug. 13, pending weather conditions.
Phase 3 will begin for Winterset Drive on Aug. 14. Starting the week of Aug.18, Phase 3 will begin for Barbara Drive, Joanne Lane, Nelson Drive, Diane Drive and Church Lane. These projects will be weather dependent.
Phase 3 will begin for Pioneer Road starting the week of Aug. 25.
Phase 3 will begin for Royal Oaks Drive on Aug. 13, pending weather conditions.
Phase 3 will begin for Winterset Drive on Aug. 14. Starting the week of Aug.18, Phase 3 will begin for Barbara Drive, Joanne Lane, Nelson Drive, Diane Drive and Church Lane. These projects will be weather dependent.
Phase 3 will begin for Pioneer Road starting the week of Aug. 25.
Share July 31 project update on FacebookShare July 31 project update on X (formerly Twitter)Share July 31 project update on LinkedinEmail July 31 project update link
Phase 3 complete for Birchwood Lane, Carleton Road and Arlington Drive.
Phase 3 will begin on Royal Oaks Drive, Merilee Rive and Valley Road the week of Aug. 3, weather permitting.
Phase 3 complete for Birchwood Lane, Carleton Road and Arlington Drive.
Phase 3 will begin on Royal Oaks Drive, Merilee Rive and Valley Road the week of Aug. 3, weather permitting.
Share July 23 project update on FacebookShare July 23 project update on X (formerly Twitter)Share July 23 project update on LinkedinEmail July 23 project update link
Phase 2 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 3 delayed due to weather.
Phase 2 complete for Royal Oaks Drive, Merilee Drive, and Valley Road. Phase 3 delayed due to weather.
Phase 1 is in progress for Winterset Drive, Barbara Drive, Joanne Lane, Diane Drive, Nelson Drive, Church Lane, and Pioneer Road.
Phase 2 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 3 delayed due to weather.
Phase 2 complete for Royal Oaks Drive, Merilee Drive, and Valley Road. Phase 3 delayed due to weather.
Phase 1 is in progress for Winterset Drive, Barbara Drive, Joanne Lane, Diane Drive, Nelson Drive, Church Lane, and Pioneer Road.
Share July 11, project updates on FacebookShare July 11, project updates on X (formerly Twitter)Share July 11, project updates on LinkedinEmail July 11, project updates link
Phase 3 complete for Maywood Lane and Jane Lane.
Phase 1 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 2 in progress.
Phase 1 will begin today on Valley Road heading East into Winterset Drive to the Barbara Drive neighborhood. Parking restriction will resume.
Phase 3 complete for Maywood Lane and Jane Lane.
Phase 1 complete for Carleton Road, Arlington Drive, and Birchwood Lane. Phase 2 in progress.
Phase 1 will begin today on Valley Road heading East into Winterset Drive to the Barbara Drive neighborhood. Parking restriction will resume.