Share 2026 Mill and Pave project on FacebookShare 2026 Mill and Pave project on X (formerly Twitter)Share 2026 Mill and Pave project on LinkedinEmail 2026 Mill and Pave project link
The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.
Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.
Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.
Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.
Street overlay projects proceed as follows:
Pre-phase
Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion
Phase I
The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase
Phase II
Manholes and gate valves are raised to accommodate new the new layers of asphalt.
Phase III
A new layer of asphalt is applied to the roadway.
The 2026 Mill and Pave project continues some areas from the 2025 Mill and Overlay Residential project.
Mill and pave projects extend the life of the existing roadway. Each summer, Minnetonka Public Works overlays new asphalt on city streets due normal to wear and tear. City engineers review street quality and select streets for maintenance based on the city's street management plan. Depending on street condition, streets are typically overlaid every 15-20 years. Residents are not assessed for these projects.
Access to properties will be maintained throughout the project. The exception is if concrete curb and gutter need replacing in front of your driveway. You will be contacted by Public Works before the project begins in this case.
Public Works staff will direct drivers during the milling and overlay process, and will assist residents as they navigate to their property.
Street overlay projects proceed as follows:
Pre-phase
Sections of settling or failed concrete curb and gutter are removed and replaced. The right of way may be impacted in this process. Yards and landscaping will be restored after completion
Phase I
The road is milled down approximately 1.5 inches along the curb line. Drainage issues are reviewed in this phase
Phase II
Manholes and gate valves are raised to accommodate new the new layers of asphalt.
Share July 1, project update on FacebookShare July 1, project update on X (formerly Twitter)Share July 1, project update on LinkedinEmail July 1, project update link
Area 1 is complete
All phases in Area 2 have been delayed due to weather conditions.
Maywood Lane, Jane Lane- Phase three delayed due to weather
Carleton Road, Birchwood Lane, Arlington Drive, Royal Oaks Drive, Merillee Drive, Valley Road and Pioneer Drive- Phase one and two in progress
Winterset Drive, Diane Drive, Barbara Drive, Joanne Lane and Church Lane- Parking restrictions lifted until further notice.
Area 1 is complete
All phases in Area 2 have been delayed due to weather conditions.
Maywood Lane, Jane Lane- Phase three delayed due to weather
Carleton Road, Birchwood Lane, Arlington Drive, Royal Oaks Drive, Merillee Drive, Valley Road and Pioneer Drive- Phase one and two in progress
Winterset Drive, Diane Drive, Barbara Drive, Joanne Lane and Church Lane- Parking restrictions lifted until further notice.
Share June 18, project update on FacebookShare June 18, project update on X (formerly Twitter)Share June 18, project update on LinkedinEmail June 18, project update link
Phase 3 complete on Maple Ridge Court (area 1). Phase 3 to beginning week of June 23, weather permitting.
Phase 1 to beginning in area 2 beginning the week of June 23
Phase 3 complete on Maple Ridge Court (area 1). Phase 3 to beginning week of June 23, weather permitting.
Phase 1 to beginning in area 2 beginning the week of June 23
Share June 10, project update on FacebookShare June 10, project update on X (formerly Twitter)Share June 10, project update on LinkedinEmail June 10, project update link
Area 1
Area P1 will be completed today. Area P2 start date has yet to be determined due to weather conditions later this week.