Whitegate Force Main Replacement project

Share Whitegate Force Main Replacement project on Facebook Share Whitegate Force Main Replacement project on X (formerly Twitter) Share Whitegate Force Main Replacement project on Linkedin Email Whitegate Force Main Replacement project link

Project summary

The City of Minnetonka will replace an old four-inch diameter force main located along Whitegate Lane and connecting to a sanitary manhole on County Road 15 (Gleason Lake Road). The force main was constructed in 1973 and has reached the end of it service life. Teams will install a new six-inch force main.

The new main will be horizontally and directionally drilled (HDD) parallel to the existing force main. HDD installation methods significantly reduce impacts to traffic, pavement, green space and surrounding infrastructure. The process utilizes a rig to pull new sections of force main into place with minimal disruption to surface improvements. It only requires pits to be excavated at significant bends or high points. Additionally, the existing force main will remain in service during construction.

Traffic Impacts

Access to homes will be maintained during the project with the exception of short periods of construction activities. A two-week closure of County Road 15 (Gleason Lake Road) is expected using Hwy 12 and Interstate 494 as a detour.

Project schedule

Construction is expected to begin on Aug. 24, and is expected to be completed by the end of September.

Will I be assessed for this project?

No. This project will be paid for through the city's utility fund.

Follow project

Sign up for text and email notifications by clicking the Follow Project widget.

Project summary

The City of Minnetonka will replace an old four-inch diameter force main located along Whitegate Lane and connecting to a sanitary manhole on County Road 15 (Gleason Lake Road). The force main was constructed in 1973 and has reached the end of it service life. Teams will install a new six-inch force main.

The new main will be horizontally and directionally drilled (HDD) parallel to the existing force main. HDD installation methods significantly reduce impacts to traffic, pavement, green space and surrounding infrastructure. The process utilizes a rig to pull new sections of force main into place with minimal disruption to surface improvements. It only requires pits to be excavated at significant bends or high points. Additionally, the existing force main will remain in service during construction.

Traffic Impacts

Access to homes will be maintained during the project with the exception of short periods of construction activities. A two-week closure of County Road 15 (Gleason Lake Road) is expected using Hwy 12 and Interstate 494 as a detour.

Project schedule

Construction is expected to begin on Aug. 24, and is expected to be completed by the end of September.

Will I be assessed for this project?

No. This project will be paid for through the city's utility fund.

Follow project

Sign up for text and email notifications by clicking the Follow Project widget.

  • Restoration work continues

    Share Restoration work continues on Facebook Share Restoration work continues on X (formerly Twitter) Share Restoration work continues on Linkedin Email Restoration work continues link

    This week’s progress included:

    • Abandonment of old force main

    Next week’s activities include:

    • Restoration will continue
    • Remaining clean up and punch list items

    This week’s progress included:

    • Abandonment of old force main

    Next week’s activities include:

    • Restoration will continue
    • Remaining clean up and punch list items
  • Eastbound Gleason Lake Road to open Saturday

    Share Eastbound Gleason Lake Road to open Saturday on Facebook Share Eastbound Gleason Lake Road to open Saturday on X (formerly Twitter) Share Eastbound Gleason Lake Road to open Saturday on Linkedin Email Eastbound Gleason Lake Road to open Saturday link

    Eastbound Gleason Lake Road (CR 15) will reopen Saturday, Sept. 12.

    This week's progress included:

    • Drilling completed
    • Curb completed
    • Paving completed

    Next week's activities include

    • Continued restoration
    • Remaining punch list and clean-up items

    Please be aware of traffic control changes and watch for changing traffic patterns

    Eastbound Gleason Lake Road (CR 15) will reopen Saturday, Sept. 12.

    This week's progress included:

    • Drilling completed
    • Curb completed
    • Paving completed

    Next week's activities include

    • Continued restoration
    • Remaining punch list and clean-up items

    Please be aware of traffic control changes and watch for changing traffic patterns

  • Lane closure continues for manhole work

    Share Lane closure continues for manhole work on Facebook Share Lane closure continues for manhole work on X (formerly Twitter) Share Lane closure continues for manhole work on Linkedin Email Lane closure continues for manhole work link

    The Gleason Lake Road (CR 15) eastbound lane will remain closed through Sept. 14 to install sanitary force main along Gleason Lake Road and make connection to a manhole.

    This week’s progress included:

    • Drilling continued
    • Manhole installed

    Next week’s activities include:

    • Drilling will be completed
    • Curb pouring
    • Restoration will begin

    Please be aware of traffic control changes and watch for changing traffic patterns.

    The Gleason Lake Road (CR 15) eastbound lane will remain closed through Sept. 14 to install sanitary force main along Gleason Lake Road and make connection to a manhole.

    This week’s progress included:

    • Drilling continued
    • Manhole installed

    Next week’s activities include:

    • Drilling will be completed
    • Curb pouring
    • Restoration will begin

    Please be aware of traffic control changes and watch for changing traffic patterns.

  • Project underway, Lane closure begins Aug. 31

    Share Project underway, Lane closure begins Aug. 31 on Facebook Share Project underway, Lane closure begins Aug. 31 on X (formerly Twitter) Share Project underway, Lane closure begins Aug. 31 on Linkedin Email Project underway, Lane closure begins Aug. 31 link

    Project began Aug. 24, 2026

    The Gleason Lake Road (CR 15) eastbound lane will be closed beginning Monday, Aug. 31 for two weeks to install sanitary force main along Gleason Lake Road and make connection to a manhole. Please see detour map here.

    This week’s progress included:

    • Locating existing utilities
    • Drilling began

    Next week’s activities include:

    • Drilling will continue
    • Pipe fusing

    Please be aware of traffic control changes and watch for changing traffic patterns.

    Project began Aug. 24, 2026

    The Gleason Lake Road (CR 15) eastbound lane will be closed beginning Monday, Aug. 31 for two weeks to install sanitary force main along Gleason Lake Road and make connection to a manhole. Please see detour map here.

    This week’s progress included:

    • Locating existing utilities
    • Drilling began

    Next week’s activities include:

    • Drilling will continue
    • Pipe fusing

    Please be aware of traffic control changes and watch for changing traffic patterns.